November 13, 2014MUNICIPALITY OF WEST ELGIN
AGENDA
COUNCIL MEETING
NOVEMBER 13, 2014
COUNCIL CHAMBERS, WEST ELGIN MUNICIPAL BUILDING
DISCLOSURE OF PECUNIARY INTEREST
ADOPTION OF AGENDA
MINUTES (Al — A5)
*October 23, 2014 Council
BUSINESS ARISING FROM MINUTES
DELEGATIONS
11:30 a.m. Consideration Meeting — Zegers Drain (under separate cover)
REPORTS (C1 -C10)
1. ROADS
a) *Monthly Report
b) *Report - 2014 -2015 Winter Schedule
2. RECREATION/EMERGENCY MANAGEMENT
a) *Monthly Report
3. WATER DISTRIBUTION SYSTEM
a) *Operations Report — October 2014
November 13, 2014 Page 2
4. WASTEWATER
a) *Rodney WTP — Operations Report Third Quarter
b) *West Lorne WTP — Operations Report Third Quarter
5. BUILDING
a) *Monthly Report
6. BY -LAW ENFORCEMENT
a) *Monthly Report
7. DRAINS
8. ADMINISTRATION
a) *Report - West Lorne Lawn Bowlers Club
b) *Report — Policy Revisions — Hours of Work
c) *WESA — Draft 2014 Fall Monitoring Report
d) *Report — Third Quarter Financial Statements
9. PLANNING
10. ACCOUNTS
CORRESPONDENCE (D1 — D18)
COUNCIL CONSIDERATION — ACTION RECOMMENDED:
1.* Jane Vanderkuyl — pickle ball at Recreation Centre;
2.* Pulmonary Hypertension Association of Canada — request for
proclamation;
3.* Minister of Employment and Social Development — response to concern
about affordable housing;
4.* *Elgin County Fire Prevention Officers Association — request for funding
for updating the Fire Safety House;
5.* Elgin County Tree Commissioner -- proposed woodlot clearing — Lot 4,
Concession 14;
6.* Elgin County OPP — criminal record checks;
November 13, 2014 Page 3
7.* Evergreen Cemetery — request for aid in maintenance of roadway;
8.* Ministry of Energy — response to wind energy;
9.* West Elgin Community Health Centre — Fall Family Fun Night;
10.* Elgin County Land Division Committee — notice of application for consent
— Dieker;
11.* Middlesex Hospital Alliance — notice of strategic planning process
consultation meeting;
12.* Elgin St. Thomas Public Health — appointment to Healthy Communities
Partnership committee;
13.* Town of Collingwood -- reconsider decision to eliminate home to home
postal delivery;
14.* Beattie Haven — emergency / evacuation centre
RECOMMENDED TO ACCEPT & FILE:
15. AMO
• POA tools and new Road Safety Bill introduced
• Watch file — October 23, 2014;
• Watch file — October 30, 2014;
• Watch file — November 6, 2014;
16. West Lincoln — Niagara Region Wind Corporation;
17. Accessibility Directorate of Ontario — appointment of Honourable David C.
Onley as Special Advisor;
18. OGRA — notice of election;
19. Ministry of Citizenship, Immigration and International Trade — nominations
for June Callwood Outstanding Achievement Award for Voluntarism in
Ontario;
BY -LAWS:
By -law No. 2014 -71 Agreement with West Lorne Lawn Bowlers Club
By -law No. 2014 -72 Amend Human Resources Policy HR -4.2
MINUTES (E1-E2)
*West Elgin Arena Board — September 9, 2014
*West Elgin Arena Board — October 14, 2014
NOTICE OF MOTION (F)
November 13, 2014 Page 4
OTHER BUSINESS (G1 —G3)
1. 2014 Ontario West Municipal Conference, December 12, 2014
2. Council announcements
3. Closed session:
• personal matters about an identifiable individual (M.A. s.239(2)(b)
• labour relations or employee negotiations (M.A. s.239(2)(d)
* information enclosed
CONFIRMING BY -LAW
ADJOURNMENT
NEXT MEETINGS:
November 27, 2014 Council
Information will be gathered in accordance with the Municipal Freedom of
Information and Protection of Privacy Act (MFIPPA). All comments and
communications received will become part of the public record unless you
expressly request the Municipality to remove it. Questions about the collection of
personal information may be directed to the Clerk.
PRESENT
STAFF PRESENT
CALL TO ORDER
MINUTES
OF THE CORPORATION OF THE
MUNICIPALITY OF WEST ELGIN
WEST ELGIN COUNCIL CHAMBERS
OCTOBER 23, 2074
Mayor Bernie Wiehle, Deputy Mayor Mary Bodnar
Councillors Norm Miller, Richard Leather
Scott Gawley, Administrator/Treasurer
Norma Bryant, Clerk
Heather James, Planner (left at 9:45 a.m.)
The Mayor called the meeting to order at 9:30 a.m. The Mayor noted that our
democracy has been hit with the attack in Ottawa and initiated a moment of silence
for those who serve us and their families.
DECLARATION OF PECUNIARY INTEREST
Councillor Miller declared a conflict of interest with item C 10 (a).
ADOPTION OF AGENDA
RES. NO. 1 Moved by Leatham
Seconded by Miller
RESOLVED that the Council of the Municipality of West Elgin
approves the agenda for October 23`d, 2014 as printed and
circulated.
DISPOSITION: Carried
APPROVAL OF MINUTES
RES. NO. 2 Moved by Bodnar
Seconded by Leatham
RESOLVED that the minutes of the meetings held on the following
date be adopted as printed and circulated:
October 9 , 2014 Council
DISPOSITION: Carried
BUSINESS ARISING FROM MINUTES:
DELEGATIONS
REPORTS
1. ROADS
2. RECREATION /EMERGENCY MANAGEMENT
3. WATER DISTRIBUTION SYSTEM
4. WASTEWATER
October 23, 2014 Page 2 of 5
5. BUILDING
6. BY -LAW ENFORCEMENT
7. DRAINS
8. WEST ELGIN PRIMARY SYSTEM
9. ADMINISTRATION
a) Report — Open Air Burning By -law
RES. NO. 3 Moved by Leatham
Seconded by Miller
RESOLVED that the report from the Clerk re: Open Air Burning By-
law be received;
AND that the revised Open Air Burning by -law be brought forward;
AND that the revised set fine schedule be approved.
DISPOSITION: Carried
b) Report — Rodney Santa Claus Parade
RES. NO. 4 Moved by Bodnar
Seconded by Miller
RESOLVED that Council of the Municipality of West Elgin supports
the request of the Rodney Santa Claus Parade Committee to close
Furnival Road from Queen Street to Victoria Street on Saturday
December 6th, 2014 from 5:30 p.m. to 6:30 p.m.
DISPOSITION: Carried
c) Report — Requests for Proposal for Landfill, Garbage and Recycling Collection
RES. NO. 5 Moved by Miller
Seconded by Leatham
RESOLVED that the report from the Adrninistrator/Treasurer re:
Request for Proposal for Landfill, Garbage and Recycling Collection
be received;
AND that the Request for Proposal be issued.
DISPOSITION: Carried
10. PLANNING
a) Report — Rezoning Application —12538 Graham Road (Dieker)
RES. NO. 6 Moved by Bodnar
Seconded by Leatham
RESOLVED that the report from the Planner re: Zoning By -law
Amendment Application for Henk and Ans Dieker, 12538 Graham
Road be received;
AND that the public meeting to be held at 9:30 a.m. on October 23,
2014 be cancelled;
AND that a decision on said application be deferred.
DISPOSITION: Carried
Councillor Miller declared a conflict of interest with the following item and joined
the audience as the property owner.
October 23, 2014 .....Page 3 of 5
b) Report — Proposed Severance — 22709 Talbot Line (N Miller)
RES. NO. 7 Moved by Leatham
Seconded by Bodnar
RESOLVED that the report from the Planner re: Proposed
Severance — Norman A. Miller, 22709 Talbot Line be received.
DISPOSITION: Carried
Councillor Miller returned to the meeting.
11. ACCOUNTS
RES. NO. 8 Moved by Miller
Seconded by Bodnar
RESOLVED that the Mayor and Administrator/Treasurer are hereby
authorized to sign Payment Voucher #9A amounting to $290,701.72
in settlement of General, Road, Water, and Arena Accounts
(including cheques #18066 - 18155)
DISPOSITION: Carried
CORRESPONDENCE:
1. Optimist Club of West Lorne — West Lorne Santa Claus Parade, November 28
RES. NO. 9 Moved by Leatham
Seconded by Bodnar
RESOLVED that Council of the Municipality of West Elgin supports
the request of the Optimist Club of West Lorne to close Graham
Road from Gilbert Street to entrance to West Elgin Secondary
School on Friday November 28th, 2014 from 7:00 p.m. to 8:00 p.m.
for the West Lorne Santa Claus parade.
DISPOSITION: Carried
2. Melanie McLeod, RAAS — funding for fall fair
Letter to be sent to Fair Board to initiate discussion before next budget.
3. West Elgin Living Water Pentecostal Church — request for fill at 9094 Graham
Road
Councillor Leatham will investigate and report back to Council.
4. Tom Campbell, Royal Canadian Legion — request for support for Military
Service Recognition Book
5. AMO
• Watch file — October 9, 2014
• Watch file — October 16, 2014
• Policy Update — Elliot Lake Inquiry Recommendations
RES. NO. 10 Moved by Leatham
Seconded by Miller
RESOLVED that the above correspondence items 2, 3, 4, 5 be
received and filed.
DISPOSITION: Carried
October 23, 2014 .....Page 4 of 5
BY -LAWS
1. By -Law No. 2014 -69 — Open Burning
RES. NO. 11 Moved by Leatham
Seconded by Bodnar
RESOLVED that the mover be granted leave to introduce a By -Law
to regulate open burning and this shall be the first and second
reading and provisional adoption thereof.
DISPOSITION: Carried
RES. NO. 12 Moved by Miller
Seconded by Leatham
RESOLVED that a By -law to regulate open burning be now read a
third time and finally passed, signed, sealed and numbered By -law
Number 2014 -69 — Open Burning
DISPOSITION: Carried
MINUTES
NOTICE OF MOTION
OTHER BUSINESS
CLOSED SESSION
RES. NO. 13 Moved by Miller
Seconded by Bodnar
RESOLVED that the Council of the Municipality of West Elgin
adjourn to a closed session to discuss:
• Litigation or potential litigation (M.A.s.239(2)(e)
DISPOSITION: Carried
RES. NO. 14 Moved by Miller
Seconded by Leatham
RESOLVED that the Council of the Municipality of West Elgin do
now rise and report.
DISPOSITION: Carried
RISE AND REPORT
The Mayor reported that direction was given to staff.
CONFIRMING BY -LAW
RES. NO. 15 Moved by Bodnar
Seconded by Leatham
RESOLVED that the mover be granted leave to introduce a By -Law
to confirm the proceedings of the meeting held on October 23`d,
2014 and this shall be the first and second reading and provisional
adoption thereof.
DISPOSITION: Carried
October 23, 2014 Page 5 of 5
RES. NO. 16 Moved by Miller
Seconded by Bodnar
RESOLVED that a By -law to confirm the proceedings of the
meeting held on October 23`4, 2014 be now read a third time and
finally passed, signed, sealed and numbered By -law Number 2014-
70— Confirming By -law October 23 2014
DISPOSITION: Carried
ADJOURNMENT
RES. NO.17 Moved by Leatham
Seconded by Miller
RESOLVED that this Regular Meeting of Council shall adjourn at
10:50 a.m. to meet again on November 13, 2014.
DISPOSITION: Carried
These minutes were adopted on the 13th day of November, 2014.
Mayor Clerk
TO:
FROM:
DATE:
SUBJECT:
The Municipality of West Elgin
COUNCIL OF THE MUNICIPALITY OF WEST ELGIN
Lee Gosnell, Public Works Superintendent
November 13, 2014
Roads Report
RECOMMENDATION:
Receive and File
INTRODUCTION:
Monthly report for October, 2014
C-1 q)
DISCUSSION:
1, Roadside mowing has been completed for the season and the second cut
along Gray Line was done on October 9th and 10th. The arm mower will be
utilized in the coming weeks to cut hard to reach areas where drifting snow
is a concern.
2. Fall grading of gravel roads and shoulders is underway (weather
permitting) and will continue into November.
3. Elgin county sign contractor completed update of all regulatory and
warning signs (on county roads) in West Elgin.
4. Additional operations carried out in October include ditching, tree removal,
catch basin repair, pothole patching and sweeping.
5. Dead /dying trees along the roadside continue to be an issue here in West
Elgin. Crews will be kept busy with tree removal /clean up during the winter
months (when not involved in winter operations).
6. All winter equipment has been checked over and serviced.
7. Staff trucked, blended and stockpiled approx. 900 tonne of sand in
preparation for winter. Salt inventory is sufficient due to left over stock
from last season.
Respectfully Submitted, Reviewed
ciKt aaa
Lee Gosnell
Public Works Superintendent
Attachments None
cott Gawley, CP 1, CGA
Ad m i n istrato r/Treas u rer
TO:
FROM:
DATE:
SUBJ ECT:
The Municipality of West Elgin
COUNCIL OF THE MUNICIPALITY OF WEST ELGIN
Lee Gosnell, Public Works Superintendent
November 13,2014
2014 -2015 Winter Schedule
RECOMMENDATION:
Receive and File
INTRODUCTION:
To provide Council with plans for West Elgin Public Works staffing schedules and
a listing of available equipment for the upcoming winter control season.
DISCUSSION:
In a continued effort to provide timely and efficient winter operations, Public
Works will be replacing last year's night shift with an early morning and afternoon
shift. This will provide continuous coverage from 3am until 1030pm Monday —
Thursday and 3am until 8pm on Friday. These new shifts will be staffed by our
fulltime operators and are in effect from December 1st until March 22nd (weather
pending).
Weekend coverage, including weather monitoring and road patrols, will continue
to be provided by 2 trained seasonal operators and will begin on November 15th.
During the period before November 15th and after March 22 "d, these duties will
be carried out by the Public Works Superintendent and/or Foreman.
As some of you are aware, one of our fulitime public works operators will be
leaving us in December to operate his own business. We would like to thank him
for his years of service and wish him well in his future endeavours.
After consideration, we have decided to fill this vacancy on a temporary basis for
the winter and then review all options regarding the full time position in the
spring.
This temporary position could be filled by a current West Elgin employee
(transferring from another department) or an outside individual hired on a
contract basis. The job is currently posted internally to see if there are any
qualified employees who may be interested.
Finally, with the addition of our new tandem axle truck in April, Public Works will
be starting the upcoming season with a full complement of winter equipment.
This includes 3 tandem axle combination units for hardtop roads, 1 single axle
combination unit for Rodney/West Lorne and 2 graders + 1 truck for all gravel
roads.
Respectfully Submitted, Reviewed by:
diez
Lee Gosnell
Public Works Superintendent
Attachments None
Scott Gawley, CP 1 GA
AdministratorlTr- - surer
TO:
FROM:
DATE:
SUBJECT:
The Municipality of West Elgin
COUNCIL OF THE MUNICIPALITY OF WEST ELGIN
Recreation Superintendent Jeff Slater
November 13 2014
Recreation Monthly Report
RECOMMENDATION:
RECEIVE AND FILE
INTRODUCTION:
Monthly report for the Recreation Department.
C -oq�
BACKGROUND:
1. The West Elgin Pool: After some extensive investigation work the
consensus is the bottom liner of the pool in all likely hood will have to be
replaced. The liner is 13 / 14 years old and has done well to last this long
in an outdoor pool. The damage is third party caused. There are actual
cuts in the liner, and there are puncture holes in the liner. The issue in not
replacing the liner and attempting to patch the liner is that if we miss some
holes the repairs are not much good at all; there are approximately 50 —
60 holes in the liner. If water builds up under the liner the liner puffs up
and this creates a significant safety hazard. Ian acquiring prices on the
new liner and will provide council a report as soon as all of the information
is available. The pool has been refilled; the hydrostatic relief valves have
been replaced and are now ready for the winter.
2. The sidewalk plows will be ready by the end of the week, both of them.
3. The arena is up and operating well and even our ice use is on the
upswing.
4. The heating concerns have been rectified at the Recreation Centre and
the floor has been recoated in the meeting room.
5. Almost all of the grass cutting has been completed, and we now are
turning our attention to cleaning up the leaves before the winter, and to
alleviate problems with the drains, all of the exterior facilities have been
winterized.
Respectfully Submitted, Reviewed by:
.24)
Jeff Slater ott Gawley, CGA: QP"A,
Recreation Superintendent Administrator/Treasurer
West Elgin Distribution System
Operations Report
October 2014
Submitted by:
Ontario Clean Water Agency
Date: November 3, 2014
CLIENT CONNECTION MONTHLY CLIENT REPORT
Facility Name: West Elgin Water Distribution System
ORG #: 1266
SECTION 1: COMPLIANCE SUMMARY
FIRST QUARTER:
JANUARY:
There were no compliance or exceedance issues reported this month.
FEBRUARY:
There were no compliance or exceedance issues reported this month.
MARCH:
The MOE final inspection report received on March 20. There was one non - compliance for the
West Elgin Distribution system for not having a drawing updated in the Municipal Drinking
Water License, the issues has now been resolved. The entire system received an inspection
rating of 99.43 %.
SECOND QUARTER:
APRIL:
There were no compliance or exceedance issues reported this month. The non - compliance
identified in the MOE inspection report was resolved, by providing the MOE the drawing on
April 25th
MAY:
There were no compliance or exceedance issues reported this month.
JUNE:
There were no compliance or exceedance issues reported this month.
THIRD QUARTER:
JULY:
There were no compliance or exceedance issues reported this month.
AUGUST:
There were no compliance or exceedance issues reported this month.
SEPTEMBER:
The distribution system received a new water works number (260094627) as part of the
separation from the Tri- County Water Treatment Plant clue to new ownership. We are waiting
on the MOE to issue new Municipal Drinking Water Licence and Drinking Water Works Permit
for the system.
FOURTH QUARTER:
OCTOBER:
There were no compliance or exceedance issues reported this month.
SECTION 2: INSPECTIONS
FIRST QUARTER:
There were no MOL inspections for the first quarter. The routine MOE inspection began on
February 4th and continued into March with the final inspection report received on March 24th,
2014.
SECOND QUARTER:
There have been no MOE or MOL inspections for the second quarter.
THIRD QUARTER:
There have been no MOE or MOL inspections for the third quarter.
FOURTH QUARTER:
OCTOBER:
There have been no MOECC (note name change Ministry of the Environment and Climate
Change) or MOL inspections for the month.
SECTION 3: QEMS UPDATE
FIRST QUARTER:
The internal audit is scheduled for April 1st.
SECOND QUARTER:
Internal Audit was conducted by Rick Turnbull on April 1st, 2014. The final audit report hasn't
been issued, once received a management review will scheduled and conducted prior to the
expected external audit in August.
THIRD QUARTER:
JULY:
The Internal Audit Report was received. There were no non - conformances and 28
opportunities for improvement identified. These were all addressed in the Management
Review that was conducted on July 21, 2014. Revisions were made to the Operational Plan
based on the audit results. The revised Operational Plan was provided to the external auditor
along with other requested documents for the external audit surveillance audit on August 1st,
AUGUST:
An external surveillance audit was conducted by Sandra Tavares on August ist in preparation for
the onsite verification audit. This audit report contained four opportunities for improvement
(OFI's). These OFI's will be addressed in next year's Management Review or when revisions are
necessary to the Operational Plan. On August 22nd, Sandra Tavares was onsite to conduct the
external audit verification audit for full scope accreditation of the system. This audit report
identified one non - conformance and three OFI's. The non - conformance was addressed and
sent back on September 2nd to SAI Global for approval and closing out. We are awaiting
response.
SEPTEMBER:
The non - conformance from the external audit conducted August 22nd was accepted and closed
out by the auditor on September 8th.
FOURTH QUARTER:
OCTOBER:
Action items from the Management Review that was conducted in July are closed off, except
for one. A draft Municipal Drinking Water Licence and Drinking Water Works Permit for the
system was provided by the MOECC, Cindy has provided a copy with her comments and
suggestions for edits to Scott for review.
SECTION 4: PERFORMANCE ASSESSMENT REPORT flee attached Round Sheets),
FIRST QUARTER;
There were no issues with water quality for the first quarter.
SECOND QUARTER:
Annual spring flushing was conducted in the system. The Rodney Tower experienced suspected
thermal turnover May 26 -27th, causing low chlorine. The area was flushed and residuals have
been resolved.
THIRD QUARTER:
JULY:
The Rodney Tower has had lower residuals, but has been managed through flushing and filling
cycles of the Tower.
AUGUST:
Chlorine residuals have been maintained at the Rodney Tower through flushing and filling
cycles. Low residuals resulted in a few call outs but didn't result in any adverse conditions.
SEPTEMBER:
The Rodney Tower chlorine residuals have been an issue but have remained in compliance by
draining and filling the tower. Adjustments were made to some autoflushers to improve
residuals at these locations (refer to Section 6). Residuals will also improve with the fall
flushing program in October and cooler temperatures.
FOURTH QUARTER:
OCTOBER:
Chlorine residuals throughout the system have improved due to cooler temperatures and fall
flushing of the system.
SECTION 5: OCCUPATIONAL HEALTH & SAFETY
FIRST QUARTER:,
There were no hazards identified during the monthly health and safety inspections conducted
this quarter.
SECOND QUARTER:
There were no hazards identified during the monthly health and safety inspections conducted
this quarter.
THIRD QUARTER:
There were no hazards identified during the monthly health and safety inspections conducted
this quarter.
FOURTH QUARTER:
OCTOBER:
There were no hazards identified during the monthly health and safety inspections conducted
this month.
SECTION 6: GENERAL MAINTENANCE
FIRST QUARTER:
JANUARY:
06, 13, 20, 27: Collected weekly bacti samples in the West Elgin distribution system
06: collected annual samples in the West Elgin distribution system
01, 03, 06, 08, 10, 13, 15, 17, 20, 22, 24, 27, 29, 31: West Elgin Facilities Checks and Readings
03, 10, 17, 24, 30: Weekly Autoflusher rounds in West Elgin
13, 20, 23: Checking Chlorine Residual at Monthly Sample Points
24: Thawed and replaced sample port on autoflusher at Crinan Line and Colley Road
FEBRUARY:
03, 10, 18, 24: Collected weekly bacti samples in the West Elgin distribution system
10: Collected Monthly and Schedule 15.1 samples
03, 05, 07, 10, 12, 18, 19, 21, 24, 26, 28: West Elgin Facilities Checks and Readings
07, 13, 20 -21, 28: Weekly autoflusher rounds in West Elgin
05: Thawed and repaired hydrant on 25172 Talbot Line, just west of Graham Rd. A damaged
ball rubber was replaced with a brand new ball rubber in order to fix the leak.
06: Fixed autoflusher wiring on Gray Line #6
06: Thawed Sample Station on Dymock Line.
18, 19: Checked Chlorine Residual at Monthly Sample Points
25: Monthly chamber meter readings
MARCH:
03, 10, 17, 24,31: Collected weekly bacteriological samples in the West Elgin distribution system
4,5,6,11,18: Monthly sample station rounds
03, 05, 07, 10, 12, 14, 17, 19, 21, 24, 26, 28, 31: West Elgin Facilities Checks and Readings
07, 14, 20, 28: Weekly auto flusher rounds in West Elgin
18, 19: Checking Chlorine Residual at Monthly Sample Points
4: Monthly chamber meter readings
4: Replaced 3 auto flusher sample taps.
i. Dymock Line and Dunborough Line
ii. Opposite 26168 Queen street
iii. Opposite 24988 Gray Line
31: Replaced broken snow flag for the hydrant at Colley and Crinan Line
SECOND QUARTER:
APRIL:
07, 14, 22, 28: Collected weekly bacti samples in the West Elgin distribution system
07: collected monthly and quarterly samples
02, 04, 07, 09, 11, 14, 16, 21, 22, 25, 28, 30: West Elgin Facilities checks and readings
04, 11, 17, 25: Weekly auto flusher rounds in West Elgin
01: Monthly chamber meter readings
01, 03, 09, 10, 22, 23: West Elgin distribution monthly blow off rounds
01, 03, 08: West Elgin Distribution monthly sample point rounds
02, 07: Removed and replaced sump pump in West Elgin North meter pit
11: shut -off water service at 22376 Downie Line for a customer to do plumbing repair inside.
Service was turned on after repair.
24: Repaired mainline isolation valve at the corner of Hoskins Line and Furnival Road. Valve was
leaking at the bonnet. Replaced bonnet bolts. No isolation was required for work to be
completed. West Elgin Municipal Works department were also involved.
MAY:
05, 12, 20, 26: Collected weekly bacti samples in the West Elgin distribution system
02, 05, 07, 09, 12, 14, 16, 19, 20, 23, 26, 28, 30: West Elgin Facilities checks and readings
02, 09, 15, 16, 23, 30: Weekly auto flusher rounds in West Elgin
01: Monthly chamber meter readings
01, 06, 26, 27, 28, 29: West Elgin distribution monthly blow off rounds
05, 06, 07, 14, 20, 26, 28: West Elgin Distribution monthly sample point rounds
05 -16- Systematic flushing and hydrant maintenance preformed on all hydrants in distribution
system
JUNE:
02, 09, 16, 23, 30: Collected weekly bacti samples in the West Elgin distribution system
02, 04, 06, 09, 11, 13, 16, 18, 20, 23, 25, 27, 30: West Elgin Facilities checks and readings
06, 13, 20, 27: Weekly auto flusher rounds in West Elgin
02: Monthly chamber meter readings
19, 24, 25, 26: West Elgin distribution monthly blow off rounds
05, 19, 25: West Elgin distribution monthly sample point rounds
THIRD QUARTER:
JULY:
07: Collected Schedule 15.1 samples taken
07: Collected Quarterly samples
07, 14, 21, 28: Collected weekly bacti samples in the West Elgin distribution system
01, 02, 04, 07, 09, 11, 14, 16, 18, 21, 23, 25, 28, 30: West Elgin Facilities checks and readings
04, 10, 18, 25: Weekly auto flusher rounds in West Elgin
02: Monthly chamber meter readings
09, 15, 17, 22: West Elgin distribution monthly blow off rounds
07, 08, 09: West Elgin Distribution monthly sample point rounds
23: repaired a broken copper line on the control valve at Rodney Tower
AUGUST:
05, 11, 18, 25: Collected weekly bacti samples in the West Elgin distribution system
01, 05, 06, 08, 11, 13, 15, 18, 20, 22, 25, 27, 29: West Elgin Facilities checks and readings
01, 08, 15, 22, 29: Weekly auto flusher rounds in West Elgin
01, 05, 12: Monthly chamber meter readings
07, 12, 13, 19, 20, 21: West Elgin distribution monthly blow off rounds
07, 08: West Elgin Distribution monthly sample point rounds
13: replaced UPS unit at Rodney Tower
21: annual testing on Backflow preventer at Rodney Tower- PASS
SEPTEMBER:
02, 08, 15, 22,29 : Collected weekly bacti samples in the West Elgin distribution system
02, 05, 08, 10, 12, 15, 19, 22, 24, 26, 29 : West Elgin Facilities checks and readings
05, 12, 19, 26: Weekly auto flusher rounds in West Elgin
03: Monthly chamber meter readings
08, 22, 23, 24, 25: West Elgin distribution monthly blow off rounds
22, 23, 25: West Elgin Distribution monthly sample point rounds
04: Check hydrant for fire event near Black's Lane
09: Assisted West Elgin contact to locate a water main along Marsh Line
15: Isolated and drained Rodney tower
15: changed duration /frequency settings on the following auto - flushers due to declining
chlorine residuals. Informed ORO and PCT of changes. All changes appear to be successful.
NY,';:gii6Ter MR '.
EAT "Fui 61' _ . 4. :.s "t
10mins /3days
F M � � a s I 4 � �4 9j 1,Y y,
10mins /7days
26168 Queens Line
Dead end of McMurchy
10mins /7days
15mins /7days
21077 Marsh Line
5mins /3days
5mins /7days
21509 Hoskins Line
5mins /7 days
15mins /7 days
16: Low Chlorine Alarm- Rodney Tower- Tower was isolated and drained until adequate
chlorine residual was reached
17: Drained Rodney Tower from Hydrant on Victoria and Sandford Street
23: A storm sewer flushing crew had a hose stuck and needed their tank filled while working on
Elm Street in West Lorne. OCWA Operator called to filled the tank twice.
29: Service repair at 11 Todd Place, temporary repair to north %" service has to be completed
after drain repair
30: Completed service leak repair at 11 Todd Place, throttled valve to keep positive pressure.
Installed %" black plastic line and 3/" shut off at main.
FOURTH QUARTER:
OCTOBER:
06, 14, 20, 27 : Collected weekly bacti samples in the West Elgin distribution system
06: Collected quarterly samples in the West Elgin distribution system
03, 06, 08, 10, 13, 14, 16, 17, 20, 24, 27, 31: West Elgin Facilities checks and readings
03, 10, 17, 24, 31: Weekly auto flusher rounds in West Elgin
31: Monthly chamber meter readings
15, 16, 17, 22, 28, 30: West Elgin distribution monthly blow off rounds
08, 14, 15, 16: West Elgin Distribution monthly sample point rounds
22 -31: Semi Annual fall hydrant inspection and flushing
SECTION 7: ALARM SUMMARY
FIRST QUARTER:
JANUARY:
07: Water pipe burst at 24992 Crinan Line in West Lorne; the operator shut off water meter tap
to stop flow to customer basement.
FEBRUARY:
No Alarms
MARCH:
March 29: Called out to 198 Graham Road for a service leak. Shut curb stop off at 9:15am and
turned service back on at 12:30, after home owner had leak repaired.
SECOND QUARTER:
APRIL:
No Alarms
MAY:
26, 27: Low Chlorine at Rodney Water Tower due to thermal turnover. Rectified by hydrant
flushing.
JUNE:
03: Low Chlorine at Rodney Water Tower due to thermal turnover. Chlorine analyzer read
0.23ppm but when tested with handheld, was 0.49ppm. Chlorine analyzer was calibrated.
07: Emergency locate for Hydro One. Hydro One called in an emergency locate at 17 Stinson
Street in Rodney due to a hydro transformer leaking oil. On call Operator located water main
near dig site, the main was outside their dig zone, and no services were close by.
THIRD QUARTER:
JULY:
27: Power failure @ Rodney Tower- Scheduled power outage- chlorine levels monitored
continuously by grab samples
AUGUST:
09, 10: Low free chlorine residual, level went into "Dead Band"
12, 13: Com -fail, replacing UPS back -up system, down for less than 1min, in co- operation with
WTP operator
16: High level at Rodney Tower, reset highlift pump at WTP
30: Low Low free chlorine residual, level went into "Dead Band" during fire event
SEPTEMBER:
14: Low Chlorine Residual at Rodney Tower. Operator on call trended chlorine residual,
dropped to 0.30 ppm. Flushed out chlorine analyzer and put back to 15 psi.
FOURTH QUARTER:
OCTOBER:
25: Called out for water service leak at 24950 Thomson Line. The leak is on homeowners side of
curbstop. Closed curbstop.
SECTION 8: COMMUNITY COMPLAINTS & CONCERNS
FIRST QUARTER:
JANUARY:
No complaints or concerns this month.
FEBRUARY:
11: Community complaint Mandy Johnson at 14084 Colley Road. Water is cloudy but clears
after a few minutes. Checked water at the autoflusher on the corner of Crinan and Colley, and
water was dear.
13: Turned off autoflusher on Thomson because water was pooling on the road and causing
hazardous conditions. PCT and ORO advised.
MARCH:
14: Received a call from the Municipality of West Elgin concerning a resident at 21486 Silver
Clay Line having no water. Suspected frozen watermain. Attempted to thaw line from house to
curb stop, then dug up curb stop. Attempted to thaw from curb stop to watermain. West Elgin
Municipal workers also assisted. It was determined the main was frozen. A short term solution
was provided to give the homeowner water. Work was performed onsite but homeowner is
still without running water.
20: Received a complaint from a resident on Beattie Line at 10:OOam. Resident claims the
water is staining the fixtures inside their home. At 11:05 the hydrant at 22938 Beattie Line was
flushed for 17 minutes and water was clear. A Chlorine sample of 1.09ppm was taken after the
hydrant was flushed.
SECOND QUARTER:
APRIL:
Resident at 21486 Silver Clay Line without water because of suspected frozen watermain.
Operator completes check (on Monday, Wednesday, and Friday of each week) of area and
attempts to run the blow off. Short -term solution for potable water remained in place during
the month. Situation resolved on May 1, 2014. Operator took samples and results were:
Free Cl2 0.78ppm, total Cl2 1.38ppm and a total flush time of 30 minutes was completed on the
line. A bacti sample also taken and sent to lab for analysis, sample came back normal.
MAY:
No complaints or concerns this month.
JUNE:
30: Responded to a customer complaint for odor in the water at 190 Munroe Street, West
Lorne. Hydrant on the corner of Munroe and Ridge St. was flushed for 15mins as well as
hydrant at the end of Monroe for 15mins.
30: Responded to a customer complaint of a service leak at 7 Todd Place, West Lorne. Water
was leaking from curb box. Two services were repaired at the same site. After services were
repaired, hydrant at 22 Todd Place was flushed. Bacti samples were taken after repair, and
24hrs after repair.
THIRD QUARTER:
JULY:
01: Received complaint of a service leak at 7 Todd Place in West Lorne. Water was leaking from
curb box. Two services were repaired at the same site. After repair was completed, hydrant in
front of 22 Todd Place was flushed. Bacti samples were taken 24 hours apart upstream and
downstream from repair.
07: Met with Operators from Municipality of Dutton /Dunwich at 401 eastbound service centre
to respond to low pressure complaints. Interconnecting valve between Eastbound and
Westbound was opened.
11: Operator onsite with plumber at 401 Eastbound service centre to observe the removal of a
backflow preventer for pressure issues.
AUGUST:
11: Community complaint received from 190 Munroe St. in West Lorne. Customer was
complaining of "fish smell" in water. Hydrant at 222 Munroe St. was flushed for 30mins with a
residual of 1.37ppm obtained. Notified ORO, as this is a repeat problem. Discussed monthly
flushing at that hydrant.
20: responded to a customer complaint at 13279 Graham Rd. Customer complained of low /no
pressure. Upon investigation it was clear it was on the homeowner's property. Notified West
Elgin Municipality of issues. Notified ORO.
29: Responded to a community complaint at 104 Sexton St. in West Lorne. Customer
complained of black particles in the water. The hydrant at the dead end of Sexton was flushed
with visual sample taken at the start of flushing. No particles were present. The hydrant was
flushed for 30mins with free chlorine residual of 1.45ppm obtained. Notified customer that it
appeared the particles where coming from within his residence.
SEPTEMBER:
23: Community complaint received from 190 Munroe St. in West Lorne. ORO and PCT
accompanied operator to the customer's house, as this has been an ongoing issue. No
problems at other homes or at the hydrant. A Pet - Bottle was given to customer and he was
instructed to give us the sample when it happens again.
26: West Elgin Municipality called to notify regarding a service leak at 11 Todd Place.
FOURTH QUARTER:
OCTOBER:
03: Customer at 24738 Thomson Line complained of leak at meter box. Arrangements have
been made for repair.
Rodney Wastewater Treatment Plant
Operations Report
Third Quarter 2014
Submitted by:
Ontario Clean Water Agency
Date: October 30, 2014
Facility Information:
Facility Name:
Facility Type:
Classification:
Operational Description:
Service Information
Areas: Serviced:
Design Capacity:
Total Design Capacity:
Total Annual Flow:
Average Day Flow:
Maximum Day Flow:
Treatment Process:
Effluent Receiver
process
Major Process
Phosphorus Removal
Additional Treatment
Discharge Mode
Effluent Disinfection Practice
Sludge Stabilization
Sludge Disposal
Additional Process Info:
Contacts:
Senior Operations Manager:
Business Development Manager:
Rodney Wastewater Treatment Plant
Municipal
Class 2 Wastewater Collection, Class 2 Wastewater Treatment
The collection system consists of sewers and one submersible pumping station. The treatment facility
main elements are an extended aeration process designed for combined carbon removal and
nitrification. The discharge of secondary clarifier: effluent is filtered and disinfected with ultraviolet light
before being re- aerated and discharged to the Sixteen Mile Creek. The waste activated sludge is
discharged to a lagoon for storage. Dual -point chemical addition alum: Is used for phosphorus
removal. Sodium hydroxide is added for control of alkalinity.
Village of Rodney
0.590 1000 m3lday:
129 1000 m3 /year:
0.353 1000 m3/day:
0.791 1000 m3/day:
Sixteen Mile Creek to Lake Erie
Features
Extended aeration
Continuous, Use of alum
Effluent filtration
Continuous discharge
UV Disinfection
Lagoon storage
Sludge is stored in lagoons; supernatant from lagoons is retreated in the plant, then released.
Dale LeBritton 519: 768 -9925, cell 519: 476 -5898
Susan Budden 519: 680 -1310 x 7003
2
SECTION 1: COMPLIANCE SUMMARY
FIRST QUARTER:
The nitrification process was inhibited due to a lower pH and temperature of the wastewater
treatment plant contents. Upon recognizing the pH drop, the alum dose was lowered to bring the pH
above 8, while remaining in compliance with total phosphorus concentrations. The Rodney
Wastewater Treatment Plant has surface aerators that contribute to lowering the temperature of the
contents within the plant. The combination of low pH and temperature contributed to non -
compliances for the month of February. While we have recovered pH, the low temperatures remain
an issue beyond our control. The mixed liquor suspended solids within the aeration tanks are being
increased in an effort to regain a larger population of nitrifying bacteria. We slowly saw
improvements in the results of total ammonia, however, the WWTP was not able to recover from the
non- compliances for the month of February due to the cold temperatures continuing into March.
The effluent temperature on March 4 was 0.8 °C and the final sample taken on March 31 has seen a
rise to 6.1 °C. Several attempts were made to reduce the impact of the colder temperatures which
included seeding the aeration tank with mixed liquor from the West Lorne WWTP, adding sugar to
the plant to provide a carbon source to activate the nitrifying bacteria and monitoring throughout
plant processes. With this rise in air temperature the Rodney WWTP began nitrifying to compliance
limits into April.
The table below shows the specific non - compliances that were reported for the Rodney WWTP for
February and March:
Unionized
Ammonia
Total Ammonia
as Nitro en
Total Ammonia
as Nitro en
2014 -02
2014 -02 -20
Unionized
Ammonia
Unionized
Ammonia
Total Ammonia
as Nitro en
2014 -02
2014 -03
2014 -03 -04
Monthly average
Single sample
Monthly average
Composite
Composite
2014 -03 -19
2014 -03
Monthly average
Single sample
Single sample
Composite
Monthly average
Composite
9mg /L
Composite
Composite
Composite
SECOND QUARTER:
There were no compliance issues for the second quarter.
THIRD QUARTER:
There were no compliance issues for the third quarter.
0,4mg!L
3.4kg /d
5mgIL
14.4mg /L
0.58mg /L
0.1 mg /L
0.23mgIL
2.2kgld
5mg/L
6.4kg/d
0.1 mg /L
0.1mg /L
2.2kgld
3
SECTION 2: INSPECTIONS
FIRST QUARTER:
There were no MOL inspections during the first quarter. The MOE continued the routine inspection
of the system which started December 4, 2013. The inspection report was received on January 315,
2014. There were four non - compliances with regulatory requirements identified in the report. They
were the following:
1. The sewage works effluent sample results did not demonstrate compliance with
microbiological parameter limits prescribed by the Environmental Compliance Approval.
The geometric mean for E. coli in April 2009 was 232 cfu /100m1 which exceeded the limit of
200cfu /100mI listed in the Environmental Compliance Approval ECA: 3- 0871 -88 -949. The E.
coli effluent limit exceedance in April 2009 was due to only one sample being taken during
the month upon start up of the system. The system was cleaned and there were no issues for
the rest of the disinfection period. The E. coli effluent limit exceedance in April 2009 was
based on only one sample being taken during the month upon start up of the system. The
system was cleaned and there were no issues for the rest of the disinfection period.
Actions: Required: The E. coli effluent limit exceedance in April 2009 was based on only one
sample being taken during the month upon start up of the system. The system was cleaned
and there were no issues for the rest of the disinfection period.
2. The overall responsible operator had not been designated for the wastewater treatment
and collection works.
Section 151: of Ontario Regulation 129/04 Licensing of Sewage Works Operators: states that
the owner of a facility shall designate as overall responsible operator of the facility an
operator who holds a licence that is applicable to that type of facility and that is of the same
class as or higher than the class of the facility. For example, the overall responsible operator
of a Class 111 wastewater treatment facility must be an operator who holds a Class III or Class
IV wastewater treatment facility operator's licence. The operating authority currently
operates the wastewater treatment plant and collection system. The Municipality operated
the collection system prior to May 1, 2013. An ORO was not designated for the collection
system during the inspection review period.
Actions: Required: No further actions are required as the operating authority has taken over
the operation of both the treatment plant and the collection system as of May 1, 2013 and an
ORO has been designated for both.
3. Operators -in- charge were not designated for the wastewater treatment plant and all
associated collection works.
Section 171: of Ontario Regulation 129/04 Licensing of Sewage Works Operators: states that
the owner of a facility or a person authorized by the owner shall designate one or more
licensed operators as operators -in- charge of the facility. The operating authority currently
operates the wastewater treatment plant and collection system. The Municipality operated
the collection system prior to May 1, 2013. An operator -in- charge was not designated for the
collection system prior to May 1, 2013.
4
Actions: Required: No further actions are required as the operating authority has taken over
the operation of both the treatment plant and the collection system as of May 1, 2013 and
OTC's have been designated for both.
4. The logs and other record keeping mechanisms did not comply with the record keeping
requirements.
Section 191: of Ontario Regulation 129 /04 Licensing of Sewage Works Operators: states that
the owner of a facility shall ensure that logs or other record- keeping mechanisms are
provided to record information concerning the operation of the facility. Section 192:
stipulates that entries in the Togs or other record keeping mechanisms shall be made
chronologically. Section 193: states that no person shall make an entry in a log or other
record - keeping mechanism unless the person is an operator -in- charge or is . authorized to
make an entry by the owner or an operator -in- charge. Records provided during the
inspection verified that the owner of the wastewater treatment plant ensured that logs or
other record - keeping mechanisms were provided to record information concerning the
operation of the facility, in accordance with the requirements of section 19 of Ontario
Regulation 129/04. However, with the exception of the pumping station, there was no record
keeping for record keeping for the remainder of the collection system prior to May 1, 2013.
As per s. 191: of 0. Reg. 129/04, the owner of a facility shall ensure that logs or other record -
keeping mechanisms are provided to record information concerning the operation of the
facility.
Actions: Required: No further action as the owner has now indicated that the operating
authority has record keeping mechanisms for both the treatment facility and the entire
collection system.
All non - compliances have been addressed and no further actions are required.
SECOND QUARTER:
There were no MOE or MOL inspections during the second quarter.
THIRD QUARTER:
There were no MOE or MOL inspections during the second quarter.
SECTION 3: PERFORMANCE ASSESSMENT REPORT (see attached):
FIRST QUARTER:
The first quarter there were 7 non - compliances with effluent limits reported to the MOE as identified
in Section 1 for ammonia in the months of February and March. The objectives identified in the
Environmental Compliance Approval were exceeded for ammonia during this same time. In January
there were 3 design flow exceedances, in March there was one design flow exceedance. The higher
flows were due to snow melt and rain. Despite these flow objective exceedances, the flow is down
by 20% from the first quarter in 2013.
5
SECOND QUARTER:
There were 3 design flow exceedances in April. These higher flows are attributed to rainfall
infiltration of the system. Despite the flow objective exceedances, the flow is down 5% from April
2013 flows.
THIRD QUARTER:
There were 4 design flow exceedances in September, they were all attributed to rainfall. Overall, the
flows were increased by 16.9% for 2014 compared to the end of the third quarter in 2013. There
were higher total phosphorous concentrations in the effluent than normal. This was due to dosing
issues using a day tank instead of the normal tank and breakage on the injection lines. The alum
storage tank requires extensive cleaning (completed in October).
SECTION 4: OCCUPATIONAL HEALTH & SAFETY
FIRST QUARTER:
JANUARY:
There were no Health and Safety issues identified this month.
FEBRUARY:
There were no Health and Safety issues identified this month.
MARCH:
Wooden stairs on both sides of clarifier need new wood as wood is chipping off and gaps between
cement stair and wooden frame.
SECOND QUARTER:
There were no Health and Safety issues identified this quarter.
THIRD QUARTER:
There were no Health and Safety issues identified this quarter.
SECTION 5: GENERAL MAINTENANCE
FIRST QUARTER:
JAN UARY:
03: Installed new heat trace on alum tank section line
09: Worked on Alum feed line
10: Finished Alum line repairs
13: Aeration motors #1, 2, 3, 5, 6 are all in operational order. #4 has motor mount issues. Informed
OIC of repairs.
6
13: Cleared floor drain in RAS building
20: ACU -tech on site inspecting all lifting devices.
21: Started generator at Rodney Pump Station for monthly inspection; Alarm channel 4 went out.
When arrived at pump station, generator has turned off. Ordered new air filter as other one was
dirty, took old air filter out and put back into auto
22: Ran generator after new air filter installed and channel 4 was called out again. Informed OIC and
ORO.
23: PCT picked up binders and logbooks from MOE inspection for filing
23: Heat trace from Alum line is too hot, unplugged for night. Informed OIC, unplugged Alum pumps
as no Alum coming out
24: Thaw out Alum line and hook up a water hose so flushing was possible
29: Clarifier was frozen, thawed out and flowing again
30: Clarifier torque light was on again, scum pit built up again and froze, cleared scum and running ok
now
30: Adjust raker arm in clarifier to prevent it from getting hung up
FEBRUARY:
10: Raised and hosed down sand filters and effluent trough
12: Added Sodium Hydroxide to raw channel to pump up pH in aeration and plant
13: PH for aeration tanks and final effluent has come back up to 8.5
17: Left East lances up for the night
18: Put lances back down and hosed down
19: Alum was not flowing, tried to flush backwards with no result. Cleaned sampler line and jug with
hot water, took samples to check for ammonia problems
20: Brought up ail lances for a few hours to get sand moving, worked on replacing valves and alum
line for alum tank. Problem discovered at the bottom of the tank, it has solidified
21: Turned valve to bypass clarifier effluent to lagoon; hosed down middle of clarifier and clarifier
weirs and put lances back down. Hosed down V -notch after clarifier, stopped bypassing to lagoon.
Measured lagoon at 9" before bypassing and 85" after
21: Set up portable totes in RAS building to store Alum, drain from outside storage tank. Made up
poly lines from tote tank to alum pump and started dose of 33 mL /min at 18:45. Pumped out alum
containment area into RAS pit; approximately 2000L into pit, added about 10001 of that water to
clarifier
22: Alum rate at 30 mL /min, appears to be normal
23: Pumped 1000L of containment water to clarifier, alum dosage at 30 mL /min
24: Took effluent sample to test for ammonia, pH and DO. Ammonia is decreasing
26:Tested monthly alarms, lifted lances for 20 minutes and took sampled for ammonia testing
27: Raised lances up for the night and turned down to 10 -11 psi
28: Upon arrival, filter building basement was flooded, turned pumps on manual. Pumped down and
hosed down clarifier and cleared scum pit, put lances back down. Hosed down effluent channel
MARCH:
04: Tightened fitting on Alum injector line, bleed air out of lines, now 100% alum at a rate of 41
m1 /min
7
05: Set up Alum transfer pump to fill Alum tote
05: Triple 5 on -site at Furnival Road pump station dropping off two loads of West Lorne aeration fluid
to reseed Rodney Sewage Plant
05: Albert's Generator inspected Rodney's Pump Stations generator
07: Cleaned sand filters by using hose, turning air off and putting hose down middle of lance and
hosed down effluent through until clear
12: Sprayed down middle of clarifier and weirs
20: Turned generator on `Low Oil Pressure' light came on and generator turned off. Albert's
Generator on -site, added more oil and discovered that the oil pressure sender is faulty and seal is
broken. Started generator again and within 40 minutes Channel #4 came out; `over crank' and `over
speed' lights were on. Informed 01C /ORO
21: Filled Alum tote from big alum tank
31: Sprayed down South weirs
SECOND QUARTER:
APRIL:
01: Gerber Electric onsite and fixed contact started for aerator #3 as it was burnt out, now 5 of 6
motors working
01: Sprayed down North weir and clarifier, v -notch and brought lances up, while spraying down
bypassed to lagoon; started at 10" ended at 8 %"
02: Sprayed down and cleaned weirs, clarifier, railings and walkways and walls of aerators
03: Sprayed down weirs, clarifier, walkways and railings
04: Transferred Alum from big tank to day tank; hosed down aeration weirs and middle of clarifier
and weirs. Brought lances up and sprayed down final effluent channel
08: Aeration #4 motor had oil all over walkway, used floor absorbent and #6 had a little bit of oil too
09: Hosed down sand filters and brought lances up, sprayed down effluent channel and kept hose in
there to flush out, getting ready for UV lights
09: Put UV system in channel and changed out burnt bulbs- all OK
14: Sprayed down effluent channel
16: SCADA system had filter reject pumps faulted and alarm logger had high level, restarted on
SCADA system and on MCC- all was ok
17: Pumped out alum containment and filled alum day tank. Sprayed down clarifier weirs and middle
of clarifier
23: Changed 3 UV lights as they were burnt out. Repaired wiring under raker walkway. Installed
decant pump and hosed down final effluent channel
24: Sprayed down middle of clarifier and weirs
28: SCADA system had reject pumps faulted, when restarted on SCADA they kept faulting, when
onsite all were working after restarted on MCC
30: Channel #8 came out at 05:25 and 06:30, by the time the dialer was called, all channels were
normal; high flow due to heavy rain storm all day and night. When arrived v -notch was higher than
normal
8
MAY:
02: Filled Alum day tank
02: Hosed down aeration weirs, clarifier weirs and middle of clarifier
08: Paris from Flowmetrix calibrating flow meter
09: Hosed down UV channel
12: Hosed down sand filters and effluent channel
15: Ch #8- high v- notch- bypassed to lagoon to flush from v -notch to sandfilters- level now OK
21: Filled Alum day tank, hosed down middle of clarifier and weirs, sprayed down UV channel
21: Pumped out Alum containment
22: Start up of decant pump; 79 m3 /day
23: Furnival Rd Pump Station generator ran for monthly work order
23: No water coming out at plant from decant pump, turned off until solution found
23: Changed WAS from 2.2m3 to 2.5 m3
30: Completed all monthly alarms. Raw sampler was off, reset breaker and now OK
JUNE:
04: Sprayed down middle of clarifier and weirs, primed decant pump- nothing
05: Hosed down aeration walls and walkway, primed decant pump- nothing, filled Alum tote
11: Brought lances up and cleaned
12: Filled Alum tote
13: Turned Rodney WAS from 2.5 m3 to 2.8 m3
16: Ran pump station generator, all okay but would not turn back off- kept in auto and turned off by
itself. Turned WAS from 2.8 m3 to 3.1 m3
16: Cleaned UV lights and sprayed down UV channel while racks were out of channel
18: Brought lances up for the night
19: Hosed down clarifier weirs and middle of clarifier in morning, and again in afternoon. Sprayed
aeration tank walls, railings and walkways, and aeration weirs. Turned WAS from 3.1 m3 to 3.4 m3
20: Hosed down clarifier weirs and middle of clarifier
23: North wall filter not pulling up sand, used hose to clean out filter and rag was stuck- all OK now
24: Channel #4 alarm disabled as calling out a lot during power outages but everything was running
OK. Turned WAS from 3.4 m3 to 3.7 m3
25: Put sump pump down in reject pit to pump out north side. All pumps on Furnival Rd Pump
Station are running okay. Put channel #4 back into service — Normally Closed- tested low -level alarm,
alarm did not reach dialer. Reset Bristle in office, lights were off to communication to Building B &C.
Reboot SCADA computer, swapped lower comm. Board RPU1 but still no communication with
Building B, downloaded RPU 1.
26: Sump Pump out of reject pit to pump Alum to tote. Turned WAS from 3.7 m3 to 4.1 m3
27: Replaced injection line as it broke off
30: Completed monthly alarm checks
9
THIRD QUARTER:
JULY:
02: Hosed down sand filters and left them up.
03: Put lances back down. Alarm #08 for power fail and channel #4, reset MCC, reset backwash
pump. Kept hose in North lance to clean sand for two hours, now ok.
04: Sprayed UV channel.
09: Annual W.O. for aeration #1, 2, 3. Hosed down walkway, railing, and walls of aeration. Hosed
down clarifier weirs, middle of clarifier, and aeration weirs. Cut grass at plant.
10: Sprayed down clarifier weirs and middle of clarifier. Filled Alum tote. Completed annual W.O. for
aeration #4, 5, 6. Finished cutting grass.
10: Albert's Generator on -site for Furnival Road generator for annual inspection.
11: Cut grass around lagoon.
14: At 09:25- Power flicker, restored power, pumped out filter basement. Hosed down UV channel
and sand filters. No Alum to plant- pump was ok, injection line was leaking, replaced fitting- all ok.
Left Alum a bit higher as not sure how long plant went without Alum. Took sample to test for
phosphorus and ammonia.
16: Hosed down sand filters and UV channel. Completed monthly alarms.
17: Call out at 06:30 for Power flicker, Operator came to plant and restored power. No Alum to plant -
clogged on suction line- took apart pump, and now ok.
21: Hosed down sand filters and UV channel.
22: Low Alum to plant 20mL /min:. Injection line was leaking, took PVC piping apart and it was
clogged, replaced fittings. Phosphorus was 0.26, kept Alum at 81mL /min for the night. Brought lances
up to clean filters.
23: Put sump pump in North side of filter basement to drain. Phosphorus now at 0.16, turned down
Alum and sent samples to lab.
24: Brought lances up for 3 hours.
25: Hole in injection line. Replaced injection line. Alum now solidifying at bottom of Alum tote, raise
suction line off of Alum tote bottom, Alum now running ok. Filled Alum tote.
28: Cleaned UV lights as per work order and hosed down UV channel while a rack was out. No alum
again, flushed discharge side of pump and alum now working.
30: Sprayed down clarifier and weirs and scum trough
31: Alum pump lost prime, took pump apart and now OK. Put decant pump back into place
AUGUST:
01: Pumped down alum containment, filled alum tote and measure alum tank at 143"
05: No Suction on alum pump, unclogged injection line
07: Checked alum and it was leaking at the pump, stopped pump and flushed alum line to unclog
discharge side and primed pump
08: Put foot valve on bottom of suction line for alum, did not work as it clogged right away
11: Tried decant pump, no suction, took it apart and added more nuts and still no suction. Flushed
discharge side of alum
12: Took apart decant suction pipe and flange and used liquid gasket to seal. Running approximately
70 m3 /day
10
13: Flushed out discharge side of alum line, took apart pump and cleaned out, cleaned suction side of
injection line
14: Channel 8, high effluent at V- notch, by passed to lagoon to empty channel, must have been
clogged
15: Sprayed down clarifier at 13:30 and 14:10. Sprayed down UV channel
18: Flushed discharge side of alum, took apart pump. Mopped facility
19: Pulled both pumps at pump station and cleaned rags
21: Brought lances up for the day and sprayed them down
22: Filled diesel tank for pump station generator from 1/4 full to Y2 full
25: Pumped out valve chamber at Pump Station. Channel 4 came out, everything was OK, and
generator was still running on emergency for monthly workorder
27: Cleaned weeds around stairs, buildings and walkways. Bolted railings on stairs at filter building
and took off hazardous wooden stairs
28: Flushed alum discharge side, raised injection line in alum tote
29: Cleaned out alum tote and emptied it. Filled alum tote back up
SEPTEMBER:
02: Sprayed down UV channel. High level came out @ 13:35, arrived at Pump Station at 14:20, level
was at 9.04m, pumped down to 7.04m. High V- notch, watched it drained down. All OK.
03: Cleaned office building, filter building and RAS building. Sprayed down bar screen, aeration tank
walls, railings and walkways. Swept RAS floor. Pumped out alum containment. Sprayed down clarifier
weirs and middle, and aeration weirs. Grass cut.
04: Sprayed down UV channel and clarifier. Cleaned out RAS containment. Cleaned and sprayed alum
containment. Mop office floors, trim weeds and moved piping
05: Sprayed down aeration weirs. Removed north stairs and level out gravel. Sprayed down clarifier.
08: No alum pumping out, flushed discharge side and leaned out pump and injection line. Monthly
generator workorder completed.
11: Spray down UV channel. Filled alum tote
15: Replaced ceiling bulbs- one fixture in RAS building needs to be replaced
16: Tested monthly alarms. Flushed out alum lines and cleaned alum pump
17: Channel 8 came out- when arrived v -notch was high but slowly going down. Made sure water is
going through filter building- high flows through there also. Contacted WTP operator- flushing
hydrant into sewer causing high flows coming through the plant
18: Primed alum pump as air in discharge side of pump. Channel 8 came out- kept an eye on it,
checked filter building, high flow through there too
19: Sprayed down UV channel. Flushed out alum discharge side line and cleaned pump
22: Flushed out alum discharge line and cleaned injection side
24: Sprayed down UV channel, clarifier middle and weirs
25: Filled alum tote. No decant to plant, checked pump- it was still running but no water and very hot
to touch. Tried priming pump and unsuccessful. Lagoon level at 14 ". Pumped out alum containment
26: Put sump pump down in filter basement to pump out north side of basement
29: Flushed alum discharge side and cleaned pump. Sprayed UV channel, completed work orders for
aeration motors 1,2,3,5,6
11
SECTION 6: ALARM SUMMARY
FIRST QUARTER:
JANUARY:
No alarms this month.
FEBRUARY:
02: Sanitary well high level, used sump pump to pump down into filter reject pit. Discharge pipe split,
needs repair, will require 2 operators and a confined space entry. Alum was froze, now running.
MARCH:
No alarms this month.
SECOND QUARTER:
APRIL:
12: 10:00; Rodney power flicker, reset main breaker and reset backwash filter pumps
26: 08:45; Power flicker, reset main breaker
MAY:
21: 19:30; Power failure- reset main breaker and backwash pumps
JUNE:
24: 19:00; Power failure- reset main breaker and backwash pumps
THIRD QUARTER:
JULY:
01:06:30; Power failure, reset MCC and plant checks
AUGUST:
19: 20:22; Power outage due to thunderstorm; reset breaker, pumped down filter building, restarted
decant and primed
20: 19:50; Callout power fail at 18:55, restarted power and decant pump
SEPTEMBER:
01: 18:00; Power flicker causing Filter Building High Level Alarm, High pressure RAS alarm.
SECTION 7: COMMUNITY COMPLAINTS & CONCERNS
FIRST QUARTER:
There were no complaints or concerns for the first quarter.
SECOND QUARTER:
There were no complaints of concerns for the second quarter.
THIRD QUARTER:
There were no complaints of concerns for the third quarter.
12
dst Lorne Wastewater Treatment Plant
& Collection System
Operations Report
Third Quarter 2014
Submitted by:
Ontario Clean Water Agency
Date: October 30, 2014
Facility Information:
Facility Name:
Facility Type:
Classification:
Operational Description:
Service Information
Areas: Serviced:
Design Capacity:
Total Design Capacity:
Total Annual Flow:
Average Day Flow:
Maximum Day Flow:
Treatment Process:
Treatment Process:
Effluent Receiver
Process
Major Process
Phosphorus Removal
Additional Treatment
Discharge Mode
Effluent Disinfection Practice
Sludge Stabilization
Sludge Disposal
Additional Process Info:
Contacts:
Senior Operations Manager:
Business Development Manager:
West Lorne Wastewater Treatment Plant & Collection System
Municipal
Class 2 Wastewater Collection, Glass 2 Wastewater Treatment
The village of West Lorne Is served by an extended aeration Wastewater Treatment Plant, comprised of
aeration, clarification, filtration, disinfection and sludge disposal. Also included is the collection system
with one pumping station and a sanitary sewers system. The operations are in accordance to C of A #
3- 0442 -90 -938, which covers the entire plant including the pumping stations.
The collection system consists of sewers and one submersible pumping station. The treatment facility
main elements are an extended aeration process designed for combined carbon removal and
nitrification. The discharge of secondary clarifier: effluent is filtered and disinfected with ultraviolet light
before being reaerated and discharged to the Zoller Drain and then Brooks Creek. The waste activated
sludge is discharged to a lagoon for storage. Dual -point chemical addition alum: is used for phosphorus
removal. Sodium hydroxide is added for control of alkalinity.
Village of West Lorne
0.900 1000 m3 /day:
201 1000 m3/year:
0.550 1000 m3/day:
1.567 1000 m3lday:
Zoller Drain to Brocks Creek to Lake Erie
Features
Extended aeration
Continuous
Effluent filtration
Continuous discharge
UV Disinfection
Lagoon storage
Sludge Is stored in lagoons. Supernatant is re- treated in the plant before release.
Dale LeBritton 519: 768 -9925, cell 519: 476 -5898
Susan Budden 519: 680 -1310 x 7003
2
SECTION 1: COMPLIANCE SUMMARY
FIRST QUARTER:
There were no non - compliances with the Environmental Compliance Approval for the first quarter.
SECOND QUARTER:
There were no non - compliances with the Environmental Compliance Approval for the second quarter.
THIRD QUARTER:
There were no non - compliances with the Environmental Compliance Approval for the third quarter.
SECTION 2: INSPECTIONS
FIRST QUARTER:
There were no MOE or MOL inspections during the first quarter.
SECOND QUARTER:
There were no MOE or MOL inspections during the second quarter.
THIRD QUARTER:
There were no MOE or MOL inspections during the third quarter.
SECTION 3: PERFORMANCE ASSESSMENT REPORT
FIRST QUARTER:
There were 5 design flow exceedances for January, 1 design flow exceedance for February and 10
design flow exceedances in March. These were all due to snow melt or rain infiltration to the system.
Despite these flow exceedances the flow is down 6% from the first quarter in 2013.
SECOND QUARTER:
There were 7 design flow exceedances for April. These high flows are attributed to rainfall infiltration
to the system. The raw flow to the plant has increased 1% from April 2013.
THIRD QUARTER:
There were 3 flow exceedances in September, all are attributed to rainfall. Overall, there has been a
5% increase in flows in 2014 compared to 2013 third quarter. Suspended solids objectives were
exceeded due to increase algae growth over the summer months. Filter repair would resolve this
issue.
3
SECTION 4: OCCUPATIONAL HEALTH & SAFETY
FIRST QUARTER:
There were no Health and Safety concerns this quarter.
SECOND QUARTER:
There were no Health and Safety concerns this quarter.
THIRD QUARTER:
There were no Health and Safety concerns this quarter.
SECTION 5: GENERAL MAINTENANCE
FIRST QUARTER:
JANUARY:
03: Removed 2nd alum mixer block for winter
09: Alum pumps cleaned off alum residue
09: Closed scum pit chamber; dosed interconnecting valve from East to West Lagoon
10: Tested alarms; sanitary high level flood float needs to be replaced
10: Opened scum trough to fully fill chamber past pipes
23: Hosed down weirs and cleaned out drains from weirs
24: Pumped up Alum to flush out line, now reading 39m1 /min
27: Noticed that the skimmer on West Clarifier was not moving; chain has slipped off of sprocket.
30: Noticed that East Clarifier chain has now slipped off too.
31: Start draining west clarifier to repair flights block off inlet:
31: Turned off RAS /WAS pump from west clarifier- P107 and P108, as clarifier was draining faster than
thought
FEBRUARY:
03: Manually pump down West Clarifier for repairs, Adjust WAS from 3.30 to MAX, Adjust RAS time 8
min to MAX; 6.00 m3 to MAX. Ensure P105 and P106 are off and P107 and P108 are on. Put WAS back
to 3.30 m3, RAS back to 8 min and 6.00 m3. Turned P107 and P108 off; P105 and P106 back into auto
04: Turned P107 &P108 into auto, P106 off; Turned WAS and RAS back to MAX to drain West clarifier.
WAS /RAS pipe was frozen at elbow, got sump pump to pump tank down more. Did not work. Put WAS
back to 3,3m3, RAS back to 6.00m3 and turned P107 and P108 off.
05: West Clarifier was not able to fully empty as pipe frozen, informed ORO and put West clarifier
back in service/ filled to thaw out pipes and wait until warmer weather
05: ACU -Tech on -site inspecting all lifting devices
06: Put chain back on sprocket in East Clarifier, kept it off as gears are frozen
07: WAS turned down to 0.00 as settling test was very low. East clarifier now working and P106 is on.
Pumped out West Lorne Pump Station chamber.
11: Cleaned effluent weirs
13: Cleaned weirs and effluent channel, kept WAS off, turned P108 back into auto
4
17: Adjust waste volume from 0.00 to 1.00 m3 X3
25: Turned Rodney STP wasting down from 3.0 m3 to 2.6 m3 as MLSS results have decreased
26: Reduced WAS from 1.0 m3 to 0.5 m3 as MLSS decreased. Tested alarms for monthly alarm checks
27: Thawed out bar screen. Noticed that East Clarifier chain that runs from motor is off of second
sprocket due to ice buildup; still running properly. Turned off breaker, put second sprocket back on
chain after thawing and fixing it; turned East clarifier back into service, all OK.
28: Ice built up on sprocket again, thawed out. OK now
MARCH:
05: Primed Alum pump
05: Triple S on -site to take one Toad from West aeration tank and one load from East tank and to bring
it to Furnival Rd pump station
06: Checked all fall protection equipment for faulty hooks- all ok
10: Locked out Blower #2, as emptied oil and not right oil here
14: Cleaned screen after weirs, and cleaned effluent channel
20: Monthly work order for generator ran at Marsh Line pump station
21: Monthly work order for generator ran at Main plant
26: Alum delivery from General Chemical
27: Cleaned office, lab, bathroom and garage, and alarms tested
28: West Clarifier was almost empty when doing checks, inlet to clarifier was full of rags- cleaned all
rags and dumped in garbage bin. P106 was not running in auto, only P07 was working, therefore
draining tank all night. Put P106 back into auto and made sure tank was filling by end of shift. Sprayed
down weirs
SECOND QUARTER:
APRIL:
03: Pumped out Marsh Line Chamber
04: New batteries replaced in emergency lights
08: Restarted Alarm Logger computer as messages where coming in 6 hours late
09: Hosed down effluent channel and put UV lights in channel for season
09: Sprayers to aerators are now working
14: Hosed down effluent channel and put screen in before UV lights
16: Sprayed down clarifier and weirs
17: Sprayed down final effluent channel
18: Synced up times on SCADA computers to stop late messages on Alarm Logger
24: Hosed down final effluent channel and work trucks, tested monthly alarms
25: Main plant generator would not start, South battery was completely dead, bought a new one and
now working well
28: Cleaned screen in effluent channel, pumped out RAS chamber
29: Replaced UV bulbs, checked on UV at 12:50 the top board was smoking and smelt burnt. At 13:30
checked on it again and top board was off, tried to turn it on and started to smoke, turned whole UV
system completely off and informed OIC. OIC then took board apart and disconnected it; now only the
two middle racks of UV lights are in the channel
30: Turned WAS volume from 0.5 m3 to 1.0 m3 and hosed down final effluent channel
5
MAY:
02: Hosed down clarifier and effluent channel
05: Set wasting amount to 100,000 m3 to start repairs on West Clarifier, hosed down clarifier, weirs,
UV channel. Set plant back to operate on East Clarifier only
06: Drained the rest of West Clarifier, pumped out RAS /WAS chamber- Not quite emptied and clean.
Put plant back to operate on East clarifier only. Also turned up Alum pump to reach a higher alum
dosage
06: Flowmetrix onsite calibrating flow meter
07: Continued with draining of the West clarifier, sprayed down clarifier to help drain faster. Put plant
back to East Clarifier
08: Turned up alum to reach higher dosage, sprayed down West clarifier
09: Sprayed clown walls and extra sludge from west clarifier, now ready for repairs, sprayed down UV
channel and east clarifier weirs
12: Ran main plant generator for monthly work order, turned Alum up a little more to help with
dosage due to rain storms
13: Reconnect West Clarifier chain, add new links wherever old ones were broken and hosed down
clarifier walls and floor. Hosed down UV channel. Three flights were installed, repairs are complete
14: Started fixing West Clarifier, once half full turned P107 &P108 back into auto, east clarifier starting
to drain because of RAS being high and filling of west clarifier. No final effluent water while filling,
turned off sprayers for the night as no water
15: Both clarifiers are full and are running good, turned sprayers back on and unclogged
15: Hetek Solutions onsite to calibrate and test gas alarms in grit room- all OK
16: Cleaned UV channel, turned WAS up from 2.8 m3 to 3.8 m3 as solids are high
22: Sprayed and cleaned UV channel
23: Changed WAS from 3.8 m3 to 4.0 m3
26: Tested monthly alarms
27: Sprayed down UV channel and weirs and kept hose in channel to help flush out channel and
sprayed down Scum chamber to pumped to lagoon to start decant
27: UV ballasts now installed - all lights are working and in the UV channel
29: Marsh Line pump station generator ran for monthly work order, pumped out Marsh Line chamber
JUNE:
03: Sprayed down clarifier, weirs and UV channel
06: Sprayed down East and West clarifier wails, weirs and UV channel.
09: Hosed down UV channel
11: Sprayed down UV channel in the morning, sprayed down clarifier, weirs and UV channel in the
afternoon
13: Wasted east clarifier 3 full extra WAS cycles to decrease sludge blanket. Sprayed down East and
West clarifier and weirs
16: Completed work orders #3120150, #3120708, #3120151, #3120152, #3120153, #3120146.
17: Sprayed down all flights and chains in East and West clarifier. Sprayed down inlets of both
clarifiers, weirs and walls of algae growth in the morning. Again in the after; hosed both clarifiers,
weirs and UV channel
6
18: Completed work order #3027145 on Blower #2, switched blower duties from 1/2 to 2/1. Lockout/
tagout Blower #1, opened both sides of blower to cool before changed oil. Completed work order #
3027144 on Blower #1
19: Opened west clarifier scum trough. General Chemical on -site for Alum delivery from 1.45m to
2.85m. Turned Alum dosage up as phosphorus was climbing as per OIC. Turned WAS from 4.0 m3 to
4.1m3
20: Sprayed down UV channel in morning and afternoon
23: Cleaned lab and equipment
24: Turned WAS from 4.1 m3 to 4.2 m3. Cleaned UV channel in morning and in afternoon cleaned
clarifiers, weirs and UV channel
25: Rodney no SCADA update since 18:40 due to storm, downloaded RPU 1
26: RAS block moved a bit to equal flow as it was moved the slightest bit. Ran an extra WAS cycled
from East clarifier with both P105 and P106 running. Turned Alum up for a bit for the night as
Phosphorus high
27: Sprayed down weirs at 10:00 and 14:30, sprayed down UV channel. Turned Alum back down as it
was reading 74 ml/min
30: Cleaned UV lights and racks as per work order #3120148. Completed monthly work orders and
alarm checks
THIRD QUARTER:
JULY:
02: Sprayed down clarifier weirs and UV channel
04: Cleaned garage /office /lab, cut grass
07: Turned up alum as raining all day, cleaned UV channel, completed W.0 # 3140750, 3140745
08: Kept alum up because of rain all day again, cleaned lab and equipment
11: Sprayed down UV channel, weirs and clarifiers and cut grass around lagoon
11: Albert's Generator on -site for annual inspection for main plant generator and Marsh Line
generator
14: Tested monthly alarms
15: Used microscope for activated sludge and raw water
16: Changed WAS from 4.2m3 to 4.1 m3, sprayed down UV and clarifier weirs. Sprayed down UV
channel and Weirs again, cleaned inside of truck and box of truck
18: Swept and mopped facility
21: Sprayed down UV channel, cleaned truck
24: Cleaned UV lights and channel
28: Sprayed down clarifier weirs and UV channel
29: Sprayed down clarifier weirs
30: Emergency lights were flickering when arrived onsite, sprayer pump was off and bar screen motor
would not work. Called Hydro One to come and fix hydro line as it was tripped out at the road. Hydro
One fixed problem at 13:00, restarted pump and motor and both were up and running. Completed UV
light work order, hosed down UV channel when UV racks were out of channel- one at a time. Bell
services on -site fixing phone line- all repaired.
31: Cut grass at Marsh Line pump station, completed alarm checks at pump station. Completed all
monthly alarms
7
AUGUST:
06: Pump #1 at Pump Station tripped out, reset and put pump #2 into duty 1. Pump #1 still tripped out
after reversed it, put in Lock -Out
07: Sump pump tripped out reset it and main power went out, only half lights and some pumps.
Turned Generator on emergency and ran plant on generator until Hydro -One showed up at 12:25.
Restored power and turned generator off, restarted all pumps and lights. Sprayed down clarifier,
weirs and UV channel,
08: Sprayed down weirs and UV channel. Pulled P100 at Pump Station and unclogged it, now running
back in duty #1
11: Cleaned bathroom, office and lab. Sprayed down clarifier
15: Sprayed down clarifier flights and chains, walls of clarifier tanks and weirs. Swept facility floors,
sprayed down UV channel
18: Swept facility; office, lab, hallway, bathroom and locker room then mopped.
19: Sprayed down UV channel, installed P102 at Pump Station- Ser. # 9410043. Removed P101-
damaged power cable, oil in stator, water in oil. Cleaned bathroom. Completed work orders for P100,
P101, P102
20: Sprayed down weirs and clarifier
25: Completed work order for Marsh Line pump station generator
26: Sprayed down clarifier, weirs and UV channel.
27: East Lagoon level- 66 ", West Lagoon level- 34"
29: Sprayed down UV channel, clarifier weirs. Completed work order for UV lights. General Chemical
on -site for Alum delivery
SEPTEMBER:
02: High level at West Lorne Pump Station, when arrived level was at 2.88m, put both pumps into
hand. Level went up to 3.19m. Kept Pump #1 in hand and informed Operator on call, Pump #2 in auto.
03: Cleaned facility
04: Cleaned floors of facility, cut grass at Marsh pump station and cleaned building
05: Sprayed down UV channel, weirs and clarifier flights and chains. Completed monthly alarms.
08: Completed monthly generator work order for West Lorne main plant and Marsh pump station.
08: Comm fail at Pump Station, checked station, RPU ok, road crew cutting roadside cut Bell pedestal,
768 -1320 also dead, WLSTP phone lines ok, Ch 28 disabled on STP dialer, rearmed dialer
09: Still no communication with Pump Station on SCADA, level was 0.81m, pump 1 was on when
arrived. Called Bell services, scheduled to come out tomorrow.
10: Bell on -site at 08:45 at Pump station to fix Bell line, phone is now working, still no Communication
to SCADA.
11: Changed light bulbs in office and alum room emergency lights- all OK now, Changed light bulbs in
ON /OFF lights on MCC. Swept and mopped facility. Bell on -site at Pump Station on Marsh line fixed
data line, now have communication to pump station.
12: Sprayed weirs down and clarifier
15: Changed out burnt light bulbs in facility
17: Sprayed down weirs and clarifier
18: Sprayed down UV channel
22: Sprayed down UV channel
8
26: Blower 1 is locked out- it will not start or run. Checked fuses on blower 1 fan and reset panel,
blower now running in duty 1. Sprayed weirs in clarifier
30: Completed testing monthly alarms
SECTION 6: ALARM SUMMARY
FIRST QUARTER:
JANUARY:
06: 00:24; Power failure; emergency lighting and same panels still on, indicating a dripped phase;
Hydro One called
06: 04:30; Power restored; shut down generator
11: 08:45; West Lorne Pump station high level alarm; No power, started generator and pump #2
started, put pump #1 into hand, wet well went back to normal level, turned pump #1 back into auto.
Hydro One called. Power came back on around 10:15, shut off generator
FEBRUARY:
There were no alarms this month.
MARCH:
There were no alarms this month.
SECOND QUARTER:
There were no alarms this quarter.
THIRD QUARTER:
JULY:
There were no alarms this month.
AUGUST:
There were no alarms this month.
SEPTEMBER:
02: High level at West Lorne pump station due to heavy rain.
SECTION 7: COMMUNITY COMPLAINTS & CONCERNS
FIRST QUARTER:
There were no complaints or concerns this quarter.
SECOND QUARTER:
There were no complaints or concerns this quarter.
THIRD QUARTER:
There were no complaints or concerns this quarter.
9
TO:
FROM:
DATE:
SUBJECT:
The Municipality of West Elgin
COUNCIL OF THE MUNICIPALITY OF WEST ELGIN
JOHN NOOREN, DEPUTY CHIEF BUILDING OFFICIAL
November 13, 2014
OCTOBER BUILDING REPORT
RECOMMENDATION: RECEIVE AND FILE
INTRODUCTION: Monthly report for October, 2014
No. of Permits Issued for Month of
October
2014
2013
SFD
New /Additions /Reno
3
5
Units
Demolitions
Storage
Buildings
New /Additions
Demolitions
Garages/
Car Ports
New
2
1
Demolitions
Farm
Buildings
New /Additions
2
2
Demolitions
Other
New
1 -
Demolitions
1
_
Septic Permits
1
1
Renovations
Estimated Value for Month of October
Permit Revenue for Month of October
$ 636,500.00
$ 3,941.58
$ 332,000.00
$ 2,655.89
No. of Permits issued for year to date
2014
2013
SFD
Units
New /Additions /Reno
20
20
Demolitions
5
Storage
Buildings
New /Additions
3
8
Demolitions
Garages/
Car Ports
New
10
4
Demolitions
Farm
Buildings
New /Additions
14
15
Demolitions
Other
New /Additions
5
10
Demolitions
3
2
Septic Permits
1
5
Renovations
12
Estimated Value for Year
Permit Revenue for Year
$ 3,303,084.00
$ 19,454.66
$ 3,425,319.00
$ 24,150.86
DISCUSSION:
Inspections completed as requested and in accordance with Act.
Respectfully S 'miffed
Deputy Chief Building Official
Reviewed by:
Scott Gawley, C
Administrator/Tr- asurer
TO:
FROM:
DATE:
SUBJECT:
The Municipality of West Elgin
COUNCIL OF THE MUNICIPALITY OF WEST ELGIN
Norma I. Bryant, Clerk
November 13, 2014
By-law Enforcement Report
RECOMMENDATION:
RECEIVE AND FILE
_ INTRODUCTION:
Monthly report for October 2014
BACKGROUND:
307
Untidy yard
COMPLIANT
CLOSED
308
Grass, untidy yard
Order issued
OPEN
309
Driveway issue
COMPLAINT
CLOSED
310
Property encroachments
COMPLIANT
CLOSED
311
Untidy yard
Order issued
OPEN
312
Untidy yard
Order issued
OPEN
Respectfully Submitted,
Norma I. Bryant, HonBA, AMCT
Clerk
Reviewed by_:
Scott Gawley, CPR; CGA
Ad m i n i st r ato r/T re a s u re r
q)
TO:
FROM:
DATE:
SUBJECT:
C-)
The Municipality of West Elgin
COUNCIL OF THE MUNICIPALITY OF WEST ELGIN
Norma I. Bryant, Clerk
November 13, 2014
Lawn Bowlers Club in Miller Park
RECOMMENDATION:
THAT a by-law to authorize the signing of an agreement with West Lorne Lawn
Bowlers Club be brought forward.
INTRODUCTION:
The West Lorne Lawn Bowlers Club has submitted an application for funding to
the Ontario Trillium Foundation.
DISCUSSION:
The Ontario Trillium Foundation has requested the Lawn Bowlers Club enter into
a land use agreement with the municipality as a condition of granting funding.
West Elgin has entered into similar agreements with the Optimist Club for the use
of Miller Park for splash pad and pavilion. Attached is the form of agreement for
this project.
Respectfully Submitted, Reviewed by:
Norma I. Bryant, HonBA, AMC' :tt Gaw ey, PA, ' GA
Clerk Administrator/Trea -urer
Attachments Agreement with West Lorne Lawn Bowlers Club
AGREEMENT WITH THE WEST LORNE LAWN BOWLERS CLUB
THIS AGREEMENT made this day of , 2014.
BETWEEN:
WEST LORNE LAWN BOWLERS CLUB
HEREINAFTER CALLED "TENANT" of the first part
and
THE CORPORATION OF THE MUNICIPALITY OF WEST ELGIN
HEREINAFTER CALLED THE "MUNICIPALITY" of the
second part
WHEREAS the Municipality is the registered and beneficial owner of the lands and
premises being more particularly described as
1) Concession 9 South Part Lot 19 — Plan 199, Part Lot 106 — Miller Park in West
Lorne on the south side of Jessie Street and east side of Graham Road —
approximately .4 acres at the corner which premises are hereinafter referred to as
the property of the Municipality;
AND WHEREAS the Tenant is desirous of the right to use the lands of the
Municipality for use of a bowling club;
AND WHEREAS the Municipality deems it expedient to lease the said lands to the
West Lorne Lawn Bowlers Club, subject to the terms and conditions hereinafter set
forth;
AND WHEREAS the Municipality and the Tenant intend by this agreement to
evidence their respective rights and obligations to each other relating to the
use /improvements on the Municipalities property by the Tenant;
NOW THEREFORE THIS AGREEMENT WITNESSETH that in consideration of the
mutual covenants contained herein, and of other good and valuable consideration,
the parties hereto covenant and agree with each other as follows:
1. The Municipality agrees to tease for a specified term of 5 years the portion of
lands shown on the diagram on Schedule "A" and described in whole as
1) Concession 9 South Part Lot 19 — Plan 199, Part Lot 106 -- Miller Park in
West Lorne on the south side of Jessie Street and east side of Graham Road
— approximately .4 acres at the corner
The five -year term to begin November 1st, 2014 to October 31st, 2019
inclusive for one dollar ($1.00) per year as consideration.
2. The Municipality agrees to cover the cost of all premiums for insurance on
the leased premises.
3. That Council shall be advised, in writing, of any improvements to be made to
the property.
2 of 2
4. That any improvements or works to the property shall be in compliance with
the Ontario Building Code Act and any other applicable regulations .
5. The Tenant agrees to supply all labour and materials needed for the
improvements to the property at their own cost.
6. The Tenant agrees to use the leased premises in a tenant -like manner and
to leave the leased premises in a clean and tidy condition.
7. The Tenant will not permit anything to be done on the leased premises,
which may be deemed to be a nuisance, or by which the insurance on the
property will be increased.
8. The Tenant will not allow any refuse, garbage or other loose or objectionable
material to accumulate in or about the leased premises and on the grounds
surrounding it.
9. The option for renewal for a further time period with all conditions contained
herein is at the discretion of the Municipality.
10. This agreement shall be binding upon the parties hereto and their
successors, assigns, respective heirs, executors and administrators or until
such time as the agreement is discontinued.
IN WITNESS WHEREOF the parties have executed this Agreement this
of , 2014.
SIGNED, SEALED AND DELIVERED
IN THE PRESENCE OF
WITNESS
THE MUNICIPALITY OF WEST
ELGIN
Bernie Wiehle
MAYOR
Norma I. Bryant
CLERK
WEST LORNE LAWN BOWLERS
CLUB
Theo Long
PRESIDENT
Joan Lashbrook
Secretary
TO:
FROM:
DATE:
SUBJ ECT:
The Municipality of West Elgin
COUNCIL OF THE MUNICIPALITY OF WEST ELGIN
Norma I. Bryant, Clerk
November 13, 2014
Hours of Work — Policy Revision
c b)
RECOMMENDATION:
THAT a by-law to authorize the changes to Human Resources Policy HR-4.2 be
brought forward.
INTRODUCTION:
Human Resources Policy HR -4.2 provides the hours of work for all employees.
DISCUSSION:
The Public Works Superintendent has reported that the hours of work for the
Road Department Night Shift for the winter months is being changed. The
proposed changes are highlighted in bold on the attached.
Respectfully Submitted,
Norma I. Bryant, HonBA, AMCT
Clerk
Attachments Human Resources Policy HR -4.2
Reviewed by:
cott Gawley, CP , CGA
AdministratorlTr-asurer
MUNICIPALITY OF WEST ELGIN POLICY MANUAL
Chapter:
Human Resources
Index No.
HR -4.2
Section:
Terms of Employment
Effective Date:
Feb 17198
Subject:
Hours of Work
Revision Date:
Nov 1/14
Page:
1 of 3
1 PURPOSE:
1.01 To establish hours of work for all full -time employees.
2 POLICY:
2.01 Municipal Office
(a) Hours of work shall be Monday to Friday, 8:30 a.m. to 4:30 p.m. with one (1) hour
for lunch.
(b) Total of 35 hours per week.
(c) Each employee has the option of taking a'/ hour lunch each day for fourteen (14)
days and having the next working day off. Some rules do apply as follows:
(i) In the first year of employment these days off can be used towards a
week's vacation. Otherwise they are not to be accumulated and taken as
another week of holidays.
(ii) They can be taken as long weekends providing there is enough staff on
hand in the office.
(iii) They can be used over Christmas for the time off needed when the office is
closed.
(iv) Carry over of unused time to the next year is not allowed.
2.02 Roads Department
(a) Hours of work shall be Monday, Tuesday, Wednesday and Thursday, 7:30 a.m. to
12:00 p.m. and 12:30 p.m. to 4:30 p.m.
(b) Hours of work on Friday shall be 7:30 a.m. to 12:00 p.m. and 12:30 p.m. to 2:00
p.m.
(c) Total of 40 hours per week.
(d) Although these hours are the regular hours of the road department, there are many
times when the Municipality may be best served by altering these hours. Any such
alteration will be at the discretion of the Road Superintendent.
(e) Winter Shift
(1) Morning shift hours commence on Monday to Thursday at 3:00 a.m. to
12:00 p.m. (noon) and on Friday from 3:00 a.m. to 9:30 a.m.
(ii) Afternoon shift hours commence on Monday to Thursday at 1:30 p.m.
to 10:30 p.m. and on Friday from 1:30 p.m. to 8:00 p.m.
(iii) Winter shift hours are from mid - November to end of March of each year.
The actual start and finish date is determined by the Superintendent.
2.03 Water Department
(a) Hours of work shall be Monday, Tuesday, Wednesday and Thursday, 7:30 a.m. to
12:00 p.m. and 12:30 p.m. to 4:30 p.m.
(b) Hours of work on Friday shall be 7:30 a.m. to 12:00 p.m. and 12:30 p.m. to 2:00
p.m..
(c) Total of 40 hours per week.
(d) Although these hours are the regular hours of the water department, there are
many times when the Municipality may be best served by altering these hours. Any
such alteration will be at the discretion of the Water Superintendent.
2.04 Parks & Recreation Department
(a) Hours of work shall be: DAY SHIFT - 7:30 a.m. to 4:30 p.m.
NIGHT SHIFT — 4 :00 p,m. to 12:00 a.m.
(b) The forty (40) hours per week are averaged over the paid period. Although these
Chapter:
Section:
Subject:
MUNICIPALITY OF WEST ELGIN POLICY MANUAL
Human Resources
Terms of Employment
Hours of Work
Index No.
Effective Date:
Revision Date:
HR -4.2
Page:
Feb 17/98
Nov \1114
2 of
hours are the regular hours of the department there may be times when the Municipality
may be best served by altering these hours. Any such alteration will be at the discretion
of the Parks and Recreation Superintendent.
2.05 Overtime Pay,
(a) An hourly rated employee who works outside of their normal scheduled shift shall
be paid time and one -half (1 1/2) from 6:00 a.m. to midnight and double time from
midnight to 6:00 a.m. A minimum call out time of two hours will be paid at the
appropriate rate.
(b) The Clerk who attends special Council meeting outside of regular working hours
shall be reimbursed the equivalent to the meeting pay for Councillors. This shall
not apply to Tri County Management Committee meetings.
2.06 Call -In
(a) An hourly rated employee who is called in outside of their regular working hours
shall be paid for a minimum of two (2) hours. Call -in does not apply to the two (2)
hour period prior to the beginning of a regular shift.
2.07 Overtime Meal Allowance
(a) A meal or meal allowance of $10.00 may be provided to employees if working
overtime and will be at the discretion of the Department Head.
2.08 Banking of Overtime Hours
(a) A maximum of 80 hours per calendar year, including stand -by time, may be banked
and taken off as time in lieu at the discretion of the Superintendent. Once hours are
banked and are taken off as time in lieu they cannot be banked again.
(b) Road Department Night Shift may bank overtime hours at the regular rates as noted
in 2.05 (a) at the discretion of the Superintendent. The premium for working the
night shift shall be paid as part of wages.
(c) Banked hours are to be taken off during the year in which they were earned or they
will be paid out. Vacation hours will be used first and then banked hours when
taking time off.
3 ADMINISTRATION:
3.01 The Treasurer shall ensure this policy is followed in the calculation of wages.
MUNICIPALITY OF WEST ELGIN POLICY MANUAL
Chapter:
Human Resources
Index No.
HR -4.2
Section:
Terms of Employment
Effective Date:
Feb 17/98
Subject:
Hours of Work
Revision Date:
Nov 1/14
Page:
3 of 3
4 ATTACHMENTS:
4.01 None
Council authorization: By -law 98 -06
By -law 2003 -67
By -law 2007 -84
By -law 2010 -71
By -law 2010 -72
By -law 2011 -08
By -law 2011 -44
By -law 2013 -07
By -law 2013 -78
By -law 2014 -72
WESA
a : Metric' company
Ms. Norma Bryant
The Corporation of Municipality of West Elgin
22413 Hoskins Line, Box 490
Rodney, ON NOL 2C0
Re: West Elgin Landfill Site
DRAFT Fall 2014 Monitoring Report
Dear Ms. Bryant:
c-8)
DRAFT
November 6, 2014
Project No. W- 134718 -00 -16
The purpose of this letter is to provide a summary of the environmental monitoring activities
conducted by WESA, a division of BluMetric Environmental Inc., at the West Elgin landfill site in
the fall of 2014.
On April 11, 2012, the Ministry of the Environment and Climate Change (MOECC) issued an
amendment to the Environmental Compliance Approval (ECA) (formerly referred to as a
Certificate of Approval (CofA)) No. A051101. All sampling was conducted in accordance with
Schedule "B" of the ECA.
In 2011, the Municipality purchased a 50m wide portion of land to the south of the landfill to act
as a contaminant attenuation zone (CAZ). As a result monitoring wells MW6, MW8, MW9, and
MW12 are now considered on -site.
The amendment to the ECA discussed above also required that the Municipality purchase the
30m proposed CAZ to the east by December 31, 2013. Negotiations with the neighbouring
property owner Johnston Bros. are currently in progress. WESA understands that once the
valuation R complete the cost for purchase will be brought to council in December 2014.
Figure 1 presents a site plan and details the location of the monitoring wells.
Tel. 519 -742 -6685
Fax, 519-742-9810
WESA, a division of BluMetric Environmental Inc.
171 Victoria Street North, Kitchener, Ontario, Canada N2H 5C5
www.wesa.ca
DRAFT
W- B4718 -00 -16
November 6, 2014
In February 2013 a Preliminary Contingency and Trigger Plan was developed and provided to
the MOECC to comply with the April 2012 amendment to the ECA. The plan cannot be finalized
until the boundary to the east is known. A revised plan will be provided once the CAZ boundary
to the east is confirmed (it is proposed that this can be incorporated in the 2014 Annual
Operation and Monitoring Report).
WORK PLAN
The environmental monitoring program included:
• Completion of a Landfill Inspection and Checklist;
• Water table measurements in all monitoring wells;
• Methane readings in all monitoring wells as well as in any buildings or structures at
the Site that are founded on or below grade and are at times occupied by people; and
• Groundwater sampling and analysis.
Note as per the 2013 Annual Monitoring Report (WESA, 2014), samples from surface water
features were not collected in 2014.
Water table elevations were measured at all 15 of the groundwater monitoring wells on -site (it
should be noted that there is no MW13 on- site). Water elevation results are provided in Table 1
and methane readings are provided in Table 2.
Groundwater samples were collected and analyzed for a series of general inorganic parameters,
metals and volatile organic compounds (VOCs). The full list of parameters analyses and the
results are provided in Tables 3 and 4.
A brief discussion of the results to date is provided below.
LANDFILL INSPECITON CHECKLIST
The Municipality has received the landfill inspection checklist completed during the fall 2014
event and returned a signed copy to WESA. During the site inspection it was noted that a new
lock is needed for monitoring well MW7. The completed checklist is included in Attachment A.
WESA
cr ONleirie, company
Page 2
DRAFT
W- B4718 -00 -16
November 6, 2014
WATER LEVELS
Shallow groundwater flow on -site has been characterized by wells completed within the
waste /fill material and the native sand and gravel units (MW1 to MW14). Monitoring well
MW2D k completed within the clay layer that underlies the landfill and MW15 is completed
within a wetland and therefore is influenced by both the shallow groundwater flow system and
surface water (precipitation etc.).
The groundwater within the shallow flow ranged between 218.43 (MW10) to 217.19 (MW4)
metres above sea level (mast) in the fall of 2014. Groundwater flow on -site is generally towards
the east. Historically, there has been a mound (an area where water levels are elevated above the
immediate surrounding area) in the groundwater table located along the western property
boundary between MW5 and MW1. The mound has caused a component of the groundwater
flow in the south western corner of the site to flow towards the south (away from MW5 towards
MW10). This occurred last in the November 2011 sampling event.
However, in some more recent monitoring events, including the spring 2014 event, the
groundwater elevations at MW10 have increased to levels at or above the groundwater
elevations at MW1 and MW5.
There now appears to be a mound located in the vicinity of MW10 and causes a component of
the groundwater flow in the southern corner of the site to flow towards the north (towards
MW1 and MW5).
During the fall 2012 monitoring event, the water elevations in MW15 through MW18 were
influenced by both the shallow groundwater flow system and surface water. During September
and November 2012, the groundwater elevations in these wells indicated that water flowed east
toward MW16 and a component of flow from MW17 and MW18 flowed back towards the
north. The wetland does not extend further east beyond MW16 and therefore there was little to
no flow beyond MW16 within the wetland. It would be expected that any flow at the eastern
edge of the wetland was more towards the south. A relative assessment of water flow within the
wetland could not be completed for the spring 2014 event, as MW16, MW17 and MW18 were
decommissioned following the fall 2012 monitoring event at the landowner's request.
Page 3
a h9elnc company
DRAFT
W- B4718 -00 -16
November 6, 2014
METHANE
Methane concentrations were measured using a portable Eagle® combustible gas monitor
calibrated for methane with a Multi -gas methane sensor. Methane readings in parts per million
methane, % LEL (% of Lower Explosive Limit) and % methane were measured within the riser
pipe at each monitoring well location.
Methane concentrations were measured at 0.5% volume in MW5. This well is in close proximity
to historical and /or current land filling operations. The concentrations in the remainder of the
wells were 25 ppm or lower.
There are no buildings or structures at the site that are founded on or below grade. However,
there is a small trailer that is raised above ground and methane concentrations were measured to
be <5ppm in the nearest adjacent monitoring well.
GROUNDWATER CHEMISTRY
Leachate on -site can be characterized by high concentrations of seven leachate indicator
parameters (WESA, 2008):
• Ammonia/ Organic Nitrogen (Organic N), alkalinity, arsenic, chloride, dissolved organic
carbon (DOC), iron, and sodium
In the 2013 Annual Monitoring Report, WESA recommended the removal of Organic N from the
list of indicator parameters as it has been observed to be naturally occurring in the surface waters
within the on and off -site wetlands. This parameter is still monitored at the site; however it is
not included in the discussion below regarding indicator parameters and RUL exceedances.
The MOE Reasonable Use Policy B7 (MOEE, 1994) was established to address the quality of
groundwater on properties adjacent to potential sources of contaminants such as landfills. The
groundwater quality at the site is compared to calculated Reasonable Use Limit (RUL) based on
the background conditions on -site and the Ontario Drinking Water Standards (ODWS, 2003).
MW14 is representative of background groundwater conditions and therefore RULs for the site
have been calculated using the background concentrations from the 2010 through 2014 sampling
events at this well. Iron exceeded the RUL at background well MW14 during this and historic
sampling events. The RULs have been calculated using historical data up to an including the fall
2014 monitoring event.
Page 4
a ,Marcia' company
DRAFT
W- 64718 -00 -16
November 6, 2014
In Table 3, parameter concentrations that exceed the background concentration calculated in
MW14 as discussed above are highlighted in bold, while those concentrations that exceed the
RUL are both bolded and italicized. VOC concentrations were compared to the ODWS and
calculated RULs and exceedances highlighted in Table 4.
The following table summarizes all leachate indicator parameters measured in excess of the RUL
and the location of the monitoring well for the fall 2014 sampling event:
of RUE. Exceedances
.
Well Location
Monitoring
Well
Groundwater
Flow
Leachate indicator Parameters RUL
Exceedances
Northwest
MW1
Shallow
None
Leachate
(Landfill Footprint)
MW2
Shallow
Alkalinity, DOC, Arsenic, and Iron
.
East
MW3
Shallow
Alkalinity ,DOC, Arsenic and Iron
Southeast
MW4
Shallow
Alkalinity, DOC, and Iron
Southwest
MW5
Shallow
Alkalinity, DOC, Arsenic and Iron
South — Recently
Purchased CAZ
MW6
Shallow
Chloride, Alkalinity, DOC, Arsenic and Iron
East
MW7
Shallow
Chloride, Alkalinity, DOC and Sodium
South — Recently
Purchased CAZ
MW8
Shallow
Chloride, Alkalinity and DOC
South — Recently
Purchased CAZ
MW9
Shallow
None
Off Site
MWIO
Shallow
None
Off Site
MWI1
Shallow
Chloride, Alkalinity, DOC and Sodium
South — Recently
Purchased CAZ
MW12
Shallow
None
Off Site
MW15
Surface /Shallow
Alkalinity and DOC
Clay
MW2D
Deep
None
The analytical results observed during the monitoring event are, in general, consistent with those
historically observed and reported on -site. It is noted that the concentrations of leachate
indicator parameter chloride show an increasing trend in MW8. The chloride concentration in
monitoring well MW15 reached a maximum level in April 2014, however during this sampling
event and the two previous fall sampling events, the concentration of chloride did not exceed
the RUL.
WESA
a ome ric" company
Page 5
DRAFT
W- 84718 -00 -16
November 6, 2014
A review of wells considered upgradient of MW15 (in particular MW3, MW7 and MW11) do not
indicate a clear trend (either increasing or decreasing) with respect to chloride or other leachate
indicator parameters over a prolonged period of time.
The results of the VOC analyses are summarized in Table 4. The results of the VOC analyses had
concentrations of all parameters measured below the ODWS in the fall of 2014.
A few parameters were detected above the laboratory detection limit but below the ODWS and
followed historical trends. Benzene was noted in MW3 in October 2014; the last time it was
detected above the laboratory detection limit was September 2008. Benzene and chlorobenzene
were noted in MW5 in the spring of 2014. Both parameters have been noted in MW5 since May
2006.
The laboratory certificates of analysis are included in Attachment B.
CONCLUSIONS
The results of the groundwater monitoring indicate that general site groundwater flow is towards
the east, with a small component towards the north along the southwestern property boundary.
Evidence of the groundwater flow direction on -site is confirmed by the analytical data obtained
from wells sampled.
Leachate impacts off -site are restricted to the east and southeast. Towards the east/ southeast,
impacts were noted in the on -site well MW7 and in the off -site well MW 1. To the southeast,
leachate impacts have been noted in MW15 indicating that groundwater and leachate are likely
discharging into the wetland. Concentrations of the leachate indicator parameter chloride have
increased since MW15 was installed in 2010 (however results have fluctuated between seasons),
and exceed the RULs during most spring sampling events. Other leachate indicator parameters
(i.e. alkalinity and DOC) initially demonstrated a decrease in concentration following well
installation, however have stabilized over the last three sampling events. The wetland is an
anaerobic reducing system with enhanced de- nitrification potential /conditions and therefore acts
to provide natural treatment of the leachate.
WESA
a IMetric'rrompony
Page 6
DRAFT
W- B4718 -00 -16
November 6, 2014
RECOMMENDATIONS
The amended ECA required the purchase of the recommended CAZ to the east of the site in fee
simple by December 31, 2013. Subsequent discussions with MOECC on November 7, 2013
indicated that purchasing the water rights beneath the CAZ, as opposed to the land in fee simple,
would be acceptable. During these discussions, the MOECC indicated that an ECA amendment
must be submitted to the MOE Approvals Branch upon purchase of the water rights beneath the
CAZ. It is noted that purchase of the land rather than the water rights is currently underway. The
proposed CAZ to the east and southeast is shown on Figure 1.
The site will be sampled again in spring of 2015 to satisfy the requirement of the ECA.
A final report will be prepared detailing the results of the two 2014 monitoring events and
provided to the MOE no later than April 30th, 2015. This report will include the proposed Final
Contingency and Trigger Plan.
If you have any questions please do not hesitate to contact the undersigned.
Sincerely,
WESA, a division of BluMetric Environmental Inc.
- DRAFT --
S'rana Scholes, B.A.Sc., P.Eng. lan Macdonald, M.Sc., P.Geo.
Project Manager /Engineer Senior Hydrogeologist
Encl.
Ref 94718-00-16 Spring 2073 Monitoring /.etter DRAFT Nov 6 2014. docx
'MESA
a Metre comp*?
Page 7
CB
TO:
FROM:
DATE:
SUBJECT:
The Municipality of West Elgin
COUNCIL OF THE MUNICIPALITY OF WEST ELGIN
Scott Cawley, Administrator/Treasurer
November 13, 2014
3rd Quarter Financial Statements
RECOMMENDATION:
That Council receive and file the 2014 — 3rd Quarter Financial Report for the
Municipality of West Elgin.
INTRODUCTION:
Council adopted the 2014 Operation's Budget and Property Tax Rates at its May
8th, 2014 Council Meeting and as part of the budget process is regular quarterly
reporting of the financial results to the approved budget.
DISCUSSION:
The first page of the attached report shows the Year -To -Date Revenues and
Expenditure as at September 30, 2014 compared to 2013 Actual, 2013 Budget
and 2014 Approved Budget. The 2 "d page provides an overview of the major
variances from Budget.
The overall projection shows that West Elgin will be on Budget.
Respectfully Submitted,
. Scott Gaw
Administrato
y
Treasurer
C
MUNICIPALITY OF WEST ELGIN
2014 BUDGET SUMMARY
REVENUE (NON - DEPARTMENT SPECIFIC)
TAXATION MUNICIPAL
LOCAL.IMPROVEMENTS
PAYMENT IN LIEUS
OMPF FUNDING
•OTHER GOVERNMENT GRANTS
OTHER REVENUE
PRIOR YEARSURPLUS
TOTAL REVENUE
DEPARTMENTAL SUMMARIES
ADMINISTRATION COUNCIL
ADMINISTRATION GENERAL GOVERNMENT
BUILDING
MTO OFFICE
FIRE
POLICING SERVICES
BUILDING, PLUMBING
EMERGENCY PLANNING
BY LAW ENFORCEMENT
ANIMAL CONTROL
CONSERVATION AUTHORITY
FOUR COUNTIES TRANSIT
ROADS- MUNICIPAL AND COUNTY
SIDEWALKS
STREETLIGHTS_
SEWER MAINTENANCE
GARBAGE COLLECTION, LANDFILL,RECYCLING
HEALTH SERVICEMETERIES
WEST-4p N WATER SYSTEM
WEST, ELGIN PRIMARY WATER SYSTEM
WEST LORNE ARENA
RECREATION
PORT GLASGOW TRAILER PARK
LIBRARY
DRAINAGE,
PLANNING AND ZONING
ECONOMIC DEVELOPMENT
TOTAL DEPARTMENTAL OPERATING COSTS
TRANSFERS TO RESERVES
TRANSFERS FROM RESERVES
DEBENTURE PAYMENTS
NET 'OPERATING SURPLUS /DEFICIT
2013 2013 2014 ACTUAL
ACTUAL BUDGET as of Sept 30
- 2,944,458.27 - 2,928,608.23
- 129,740.09 - 133,570.21
- 83,605.14 - 87,000.00
- 1,861,600.00 - 1,861,600.00
0.00
- 315,013.43 - 320,180.00
- 518,178.10 - 518,178.10
- 5,852,595.03 - 5,849,136.54
- 3,149,671.75
-57,540.33
- 916,850.00
- 147,171.11
- 92,917.31
- 4,364,150.50
2014
BUDGET
-3,029,847.56
- 106,608.02
- 83,625.14
- 1,833,700.00
- 309,830.00
- 92,917.31
- 5,456,528.03
66,923.58 83,400.00 58,187.15 78,200.00
779,709.70 862,310.00 461,695.40 823,210.00
60,324.28 79,020.00 48,352.46 61,020.00
5,437.19 6,600.00 - 1,127,57 6,600.00
373,097.36 371,285.00 99,181.44 341,750.00
917,080.02 917,284.00 611,231.33 946,118.06
32,313.23 42,860.00 27,452.94 34,060.00
2,191.04 4,000.00 1,539.88 4,000.00
1,017.31 1,850.00 1,098.68 1,750.00
- 6,272.41 - 3,492.00 - 9,516.93 - 4,300.00
32,826.00 32,826.00 37,732.00 60,232.00
9,781.62 7,050.00 27,973.44 8,632.00
1,309,557.62 .1,427, 807.59 1,105,628.98 1,379,341.63
8,310.70 24,000.00 10,288.89 24,000.00
39,572.37 50,000.00 33,952.51 50,000.00
0.00 0.00 0.00 0.00
126,143.55 142,300.00 80,555.58 124,600.00
1,140.00 2,000.00 0.00 2,000.00
0.00 0.00 0,00 0.00
0.00 0.00 0.00 0.00
81,673.91 61,679.22 0.00 76,898.04
355,768.55 389,250.00 266,480.20 362,500.00
0.00 0.00 0.00 0.00
10,550.55 - 3,500.00 9,603.57 - 15,700.00
23,446.37 21,650.00 27,833.44 21,650.00
72,773.00 120,000.00 59,663.76 60,000.00
9,213.52 12, 500.00 6,834.28 11,700.00
4,312,579.06 4,652,679.81 2,964,641.43 4,458,261.73
927,440.29 622,395.10 491,943.46
- 175,000.00
133,570.21 133,570.21 22,975.27 141,945.07
- 479,005.47 - 615,491.42 - 1,376,533.80
- 364,377.77
CAPITAL EXPENDITURES
GRANT FUNDING /CONTRIBUTIONS - 261,890.36 - 264,261.40 - 4,384.69 - 165,121.31
TRANSFERS FROM RESERVES - 303,447.00 - 334,947.18 - 1,085,682.14
CAPITAL PURCHASES 951,425.52 1,214,700.00 889,534.23 1,640,934.14
CAPITAL FUNDED FROM FUND SURPLUS & OPERATIONS 386,088.16 615,491.42 885,149.54 390,130.69
NET SURPLUS
Municipality of West Elgin
- 92,917.31 0.00
- 491,384.26
25,752.92
As of Sept 30, 2014
Page 1
Municipality of West Elgin as of Sept 30, 2014
Comments:
Revenue:
Local Improvements:
YTD -To be adjusted after the final installation of final tax bill due date of Nov 25, 2014
Payment in Leius:
YTD -To be adjusted at the end of the year
Other Revenue:
Marriage License Revenue above current annual projections, Burial Permits will most likely surpass
projected revenue projections.
Bank Interest amount as of June 30, 2014 -will be recognized in 4th Quarter
County of Elgin Parking Ticket revenue to be recognized in the 4th Quarter
OMAFRA RSJS revenue expected: $2,240 and Elgin St. Thomas SJS revenue expected: $5,760
Departmental Summaries:
Administration:
Council: Based on the historical number of meetings and events attended by council and possible
additional training with Oct 2014 Election Results
Staff Inncludes: Adrninistrator /Treasurer, Clerk, Deputy Treasurer, Financial Assistant, Accounts Payable,
Receptionist/Office Clerk and Financial Accounting Clerk (allocated to the Water Department)
Some office staff mileage not yet paid, additional cost for short term reception help
Convention/Seminar includes ROMA Conference, AMCTO Annual Conference
Miscellaneuos Expenses include Association Memberships, training courses for staff succession planning
Office Supplies:
Ipads'for Council have not yet been purchased, water postage to be allocated at the end of the year.
Minor: Capital Purchases include a new printer and monitor
Capital Purchase includes: Software Upgrades $ 10,370.37 and Office Renovations YTD $13,014.97
Grants awarded by Council as of Sept 30. Tiny Tots $10,000, Arts & Cookery (Last of 3rd year commitment)
$ 25,000, and Minor Requests $8,114.49
Building:
Janitorial Wages to be allocated at the end of the year
Service Ontario:
Closed Saturdays as of Sept 20, 2014
Fire:
YTD Fire Wages and Benefits are paid in the 4th Quarter
YTD budgeted equipment, training, and vehicle expenses have yet to be made in
4th Quarter - Annual Inspections
Fire Hydrant Rental adjustment to be made in 4th Quarter
Policing:
Policing Costs are $82,429.70 per month
Building, Plumbing, Emergency Planning, By -Law Enforcement:
Decrease in Permit Revenue
Cominunity Emergency annual exercise held in West Elgin on May 1, 2014.
Joint Dutton- Dunwich/Southwold/West Elgin
Four Counties Transit:
The`Adult Day Program will only operate three days a week starting April 1, 2014. This will
reduce the amount of scheduled trips and will make the bus available for special trips twice a week.
Four County Transit increased fares on July 1, 2013. This was the first increase in seven years.
The annual actual deficit is shared between the member municipalities of West Elgin,
Southwest Middlesex, Newbury and Chatham -Kent. The Township of Dawn - Euphemia is no
longer a member of Four Counties Transportation.
The' cost of drivers and operations should see a decrease in 2014 with the number of scheduled
trips being reduced.
The grant will be received in the 4th Quarter to offset YTD expenditures
Roads:
,Unekpected repairs to Dunborough Road Culverts $ 2,885.87
Construction project costs yet to be fully realized as of Sept 30, 2014
Federal Gas Tax funding used for Kerr Road
Sidewalks and Streetlights:
West Elgin purchased new energy efficient LED streetlights on Queen's Line between
the Village of Rodney limits to the corner of Furnival.Tracking consumption and costs.
Sewage Treatment:
Sewage Capital Projects have yet to be implemented.
Garbage Collection/Recycling/Landfill:
Rodney Garbage expenditure based on contract with Ron Aubertin, Rodney Recycling
with. Jack Falkins, and West Lorne Garbage and Recycling Expenditures based on contract with BFI
New, RFP for Curbside Waste Collection Services sent out Oct 30, 2014
Port Glasgow Trailer Park:
Seasonal Park Operations -Open May to October. Trailer Fees due May 1, 2014
New work shed constructed at the park.
Area 2 Septic Bed Construction is defferred to the Spring of 2015.
Water:
YTD water totals are based on new bi- monthly water billing cycle. Water revenues are up.
New water van was purchased and put in July 2014
Water Postage to be expensed in 4th Quarter
Tri County Water:
Colour Water Study - $27,169.93
Arena:
Arena Operations and Maintenance Costs are split with Dutton - Dunwich at the end of the year.
Arena front doors have been replaced.
Parks & Recreation:
Unexpected replacement of pool heaters $14,524.92
Drainage:
YTD -grant revenues not received until year end. YTD timing of expenses
Planning and Zoning:
West Elgin hired a new Professional Planner. Planner splits time between West Elgin,
Dutton - Dunwich, and Southwold.
Transfers to Reserves:
YTD -year end allocation entry to be made
Transfers from Reserves:
YTD -year end allocation entry to be made
Debenture Payments:
YTD- Allocation made at year end
MUNICIPALITY OF WEST ELGIN
CAPITAL BUDGET 2014
ADMINISTRATION GENERAL
OFFICE RENOVATIONS
SOFTWARE UPGRADE
2014 ACTUAL 2014
as of Sept 30 BUDGET
13,014.97 20,000.00
19,370.37 10,000.00
23,365.34 30500.0L
ROADS
FGT. 23,783.09 110,000.00
TRUCK517 198,153.50 200,000.00
R- GRAVEL PIT REHAB 27,481.24 59,470.00
PICK UP 83 28,408.71 35,000.00
LOADER 818 - SCALE KIT (DEFERRED -2015) 7,500.00
GRAHAM ROAD CONSTRUCTION 125592.15 55,000.00
CARROLL LINE DRAIN -END TREATMENTS 17,881.28 30,000.60
COLLEY ROAD - RECONSTRUCTION 66,196.07 102,545.00
HENRY ROAD - RECONSTRUCTION 23,35926 60,837.00
MCDOUGALL LINE - RECONSTRUCTION WITH RAIL GUIDE 20,000.00
MUNROE ST EXT -WL (DEFERRED -2015) 7,000.00
RADIO SYSTEM 26,993.53 35,000.05
UPGRADE FOR JOHN DEERE TRACTOR 7,853.28 12,500.00
DUNEOR000H CULVERTS 2,885.87
GPS 16,659.14 18,659.14
566,547.19 751,611.14
WATER CAPITAL
WATER SERVICE VAN
TRI COUNTY WATER
COLOUR WATER STUDY
ARENA
FRONT DOOR REPLACEMENT
SPECTATOR NETTING (DEFERRED -2015)
BOARDS B EVETROUGHS (DEFERRED-2015)
PAVE (DEFERRED -2015)
24,834.33 25,000.00
24,634.33 25,000.00
27,169.93
27,169.93
6.349,46 13,400.00
10,000.00
10,600.00
8,000.00
6,,349.48 41490.00
PARKS'BRECREATION
STANDBY GENERATOR FOR EMERGENCY MANAGEMENT (DEFERRED -2015) 35,000.00
TABLES - RECREATION CENTRES (40 TABLES) 8,000.00
SOUND BARRIERS -' 5,000.00
COMPACTTRACTORMIOWERILOADER 19,820.00 30,000.00
SIDEWALK SNOW BLOWER REPLACEMENT 3,500.00
POOL HEATERS 18,510.36
SEWER MAINTENANCE CAPITAL
RODNEY
ROOF
NEW PUMP
ALUM -CHEM FEED SYSTEM REPLACEMENT '
TSSA REGULATIONS -NEW GENERATOR
REPLACE AERATION DRIVE 01
WEST LORNE
FILTER REPAIRS AT WATER TREATMENT PLANT
UV SYSTEM UPGRADE
TORQUE LIMIT SWITCHES REPLACEMENT
REPLACEMENT OF EAST CLARIFIER CHAINS, FLIGHTS 8 WARE BARS
FIRE DEPARTMENT
WEST LORNE - EXTRACATION EQUIPMENT
RODNEY - EXTRACTION EQUIPMENT
COMMUNICATIONS EQUIPMENT - RODNEY 8 WEST LORNE
PORT GLASGOW TRAILER PARK
SEPTIC SYSTEM (DEFERRED- SPRING OF 2015)
WORK SHED '
36, 30.36 81,500.05
2,000.00
8,000.00
5,005.00
5,000.00
10,000.00
60,000.00
11.000,00
8,000.00
6,500.00
0.00 115500.00
31,535.44 30,000.00
31.535.44 30,000.00
97,128,65 145 023.00
160,199.57 206,023.00
2,499.99 351,000.00
31,588,47 40,000.00
34,089.46 391,090.09
SIDEWALKS 8 STREETLIGHTS
STREETLIGHTS 10,626.60
16,829,64
TOTAL CAPITAL 659,534.23 1,640,934.14
Municipality of West Elgin As of Sept 30, 2014 Page 1
0 v' ` 14
Dear Jeff,
After enquiring at the municipal office they suggested I write to the Recreation Dept
outlining my idea with a copy to the council.
I am not sure if you have heard of the latest racquet sport called pickleball. It is quickly
becoming the fastest growing sport in Ontario.. We only heard of it last year in Florida
and were delighted to find a club in St. Thomas which we quickly joined.
The game is played on a badminton size court with a whiffle ball (about the size of a
tennis ball) and a solid smooth surface, short handled paddle larger than a ping pong
paddle. The game is easy to play and you do not have to be a great athlete to play.
I believe the schools in West Elgin are being introduced to the game by our executive
and members from St. Thomas. I thought this may be something for the Rodney Rec
Centre to offer as it is great exercise for young and old.
The start up costs would simply be the portable nets, racquets and balls which we could
provide an idea of cost if there is an interest.
We would be available to answer any further questions you might have.
Thanks for your consideration,
Jane Vanderkuyl.
Norma Bryant
From: craig and kerry pierce < craigandkerrypierce @hotmail.com>
Sent: October -21 -14 9:53 AM
To: bwiehle @elgin- county.on.ca; nbryant @westelgin.net
Subject: Request for a Proclamation
Good Morning Mayor Wiehle and Ms. Norma Bryant
-a
I am writing to request a proclamation from the municipality of West Elgin to declare November Pulmonary
Hypertention Month.
This will be a tremendous help to us in our awareness efforts on behalf of all persons throughout your
community and Canada who suffer with this rare, life threatening lung disease.
PULMONARY HYPERTENSION, or PH is a disease affecting the arteries of the lungs. It can strike anyone
regardless of age, sex, social or ethnic background. In pulmonary hypertension (which means high blood
pressure int he lungs), the arteries of the lungs become narrowed and scarred, which can result in almost
complete closing of the arteries.
People affected with this disease suffer from continuous high blood pressure in the lungs which results in an
enlargement of the heart, leading to heart failure and death.
Some symptoms of pulmonary hypertension are: shortness of breath (especially with any activity); bluish or
purplish hands, feet and lips; swelling of hands and feet; light- headed /dizziness, especially when climbing
stairs or standing up; chest pain, especially with any physical activity; feeling tired all of the time; and
sometimes even fainting.
The somewhat "generic" symptoms, as seen above, often get mistaken for other less serious illnesses and
conditions; patients therefore experience significant delays in receiving lifesaving treatments.
I am and my family are very passionate about creating awareness about helping to find a cure for PH, as our
youngest daughter 3 year old Everleigh has been battling this disease since February 2013. Rare diseases get
very little attention and are usually very difficult to diagnose, so even a proclamation and information in
media can shed some light and promote discussion among medical professionals and citizens, with the hope
of earlier diagnosis for those affected.
For more information about PH and this request, please feel free to contact me.
I know with the upcoming election it is a very busy time but I hope that you will be able to add my request to
the council agenda as soon as possible.
Sincerely,
Kerry
1
Kerry Pierce
Ambassador
Pulmonary Hypertension Association of Canada
24915 Crinan Line
West Lorne, ON NOL2P0
(519)614 -3434
kpierce @phacanada.ca
www.phacanada.ca
2
Minister of State
(Social Development)
OCT 1 4 2014
Ms. Norma I. Bryant
Clerk
The Municipality of West Elgin
PO Box 490
22413 Hoskins Line
Rodney ON NOL 2C0
Ministre d'Etat
(Developpement social)
Ottawa, Canada KM 0J9
23 2014
Dear Ms. Bryant:
1 am responding to your letter addressed to the Honourable Jason Kenney, Minister of
Employment and Social Development and Minister for Multiculturalism. You wrote concerning
a resolution passed by the Council of the Municipality of West Elgin that supports the
Federation of Canadian Municipalities' housing campaign, "Fixing Canada's Housing Crunch."
I appreciate that you have taken the time to share the Council's concerns as they relate to
affordable housing in Canada. I can assure you that we are continuing to make significant
investments in housing.
This year, through Canada Mortgage and Housing Corporation (CMHC), we will invest
approximately $2 billion in housing. This includes support for close to 600,000 individuals and
families living in existing social housing, which is provided under long -term agreements
covering a 25 to 50 year period. At the end of these agreements, the federal government will
have fulfilled its commitment and funding will end. At the same time, the mortgages on these
properties will generally be paid off, allowing many housing groups to continue to provide
affordable housing and to be free to operate their projects as they see fit.
I would also like to add that our Government is providing significant funding under the
Investment in Affordable Housing (IAH). Under the IAH, provinces and territories cost match
the federal investment and are responsible for program design and delivery. Provinces and
territories have the flexibility to invest in a range of affordable housing programs in order to
meet their local needs and priorities. Funding may be used to create new or to renovate
affordable rental housing; to improve affordability such as through rent supplements; and, to
foster safe independent living through accessibility modifications. From April 2011 to
June 2014, more than 183,600 households have benefitted from this investment nationally.
More recently, as part of Economic Action Plan 2013, the Government of Canada announced its
continued commitment to working with provinces and territories to develop and implement
solutions to housing by investing more than $1.25 billion over five years to extend the IAH to
2019.
...12
Canada
-2-
More recently, as part of Economic Action Plan 2013, the Government of Canada announced its
continued commitment to working with provinces and territories to develop and implement
solutions to housing by investing more than $1.25 billion over five years to extend the IAH to 2019.
For the Province of Ontario, this represents a combined investment of more than $801 million over
five years and was announced in August 2014. Under the IAH, Ontario has the flexibility to design
and deliver a range of affordable housing programs to address local housing needs and priorities.
The Province of Ontario is supporting the building and renovation of affordable housing, as well as
the provision of rental and homeownership assistance to low and moderate income households. A
portion of funding will be dedicated to Aboriginal households living off - reserve. Other priority
groups will include seniors, persons with disabilities and victims of domestic violence.
I would also like to draw Council's attention to CMHC's Affordable Housing Centre, which helps
create new affordable housing, including rental housing, for projects that do not rely on federal
subsidies, by offering assistance such as Seed Funding, and Proposal Development Funding.
CMHC contributes to the stability of the housing finance system by providing mortgage loan
insurance across the country, including in those markets that are less served by the private sector.
CMHC offers mortgage loan insurance with greater financing flexibilities, including loan-to -value
ratios of up to 95% and reduced premiums. These flexibilities are available for new affordable
multi -unit residential properties, including those funded under the IAH, for rental, retirement and
long -term care facilities.
The federal government also provides funding for homelessness through the Homelessness
Partnering Strategy (HPS), administered by Employment and Social Development Canada. HPS is a
community -based program aimed at preventing and reducing homelessness by providing direct
support and funding to 61 designated communities across Canada. Economic Action Plan 2013
announced $600 million in funding to extend the HPS for five years until 2019, with a focus on the
Housing First approach.
Taken together, this broad range of housing activities supports vulnerable Canadians, homeowners,
renters and the housing sector. I hope this information helps assure Council that our Government is
committed to affordable housing solutions and to assisting those in housing need.
Thank you for writing.
Yours sincerely,
The Honourable Candice Bergen, F.C., M.P.
Elgin County
Fire Prevention Officers Association
c/o 305 Wellington Street, St.Thomas, Ontario, N5R 2T2 Phone 631 -0210 Fax 631 -0215
To The Mayor and Council
Municipality of West Elgin
The Elgin County Fire Departments Fire Safety House has been a valuable tool used by fire
departments and fire associations across the County of Elgin to educate thousands of children
and adults alike in fire safety and prevention. Since 1998, the Fire Safety House has regularly
attended schools, public events and local fairs in effort to raise awareness of fire safety.
The Fire Safety House was originally purchased in 1998 and currently needs some updating
and refurbishing to ensure its continued use and success. There are minor structural needs and
some aesthetic requirements such as new flooring and painting.
We are looking for sponsors who are willing to partner with us to raise the necessary funds to
update the Fire Safety House. Our target fundraising goal is $20,000. In recognition of your
generous contributions, we offer the following in recognition of donations:
Contribution Recognition
$3,500 3' x 3' logo on the House
$2,000 1.5' x 1.5' logo on the House
$ 500 Name on the House
On behalf of the Elgin County Fire Prevention Officers Association the South Dorchester
Firemen's Association (Lyons) is taking the lead on this fundraising endeavor to continue to
promote home fire safety.
If you wish to make a donation please make cheques payable to the South Dorchester
Firemen's Association /Fire Safety House.
If you require further information or wish to make a donation please contact me at 519 -615 -7749
or by email at wdkmbradley a,gmail.com, or Captain Mike Pond at 519 - 670 -7242 or by email at
mdksiaamteiecom.net.
In the name of fire safety, we thank you
Captain Dave Bradley
Fundraising Committee Co- Chairperson
Cc: Fire Chief
Aylmer Bayham Central Elgin Dutton/Dnnwich
West Elgin St. Thomas
Malahide Southwold
El inCoun
g tY
October 24, 2014
Municipality of West Elgin
22413 Hoskins Line
P.O. Box 490
Rodney, ON
NOL 2C0
Attention: Scott Gawley, Chief Administrative Officer
RE: Proposed Woodlands Clearing on Lot 4, Concession 14
Former Township of Aldborough, Municipality of West Elgin
Under Section 135 (2) of the Municipal Act all abutting landowners shall be notified of
impending woodlot clearings.
This letter hereby notifies you of the proposed woodland clearing by Lakeview
Aldborough Bluffs Inc. The proposed clearing of 0.3 hectares (0.74 acres) on Lot 4,
Concession 14 in the Municipality of West Elgin is for the purposes of creating a
laneway access.
The Elgin County Woodlands Conservation Bylaw contains a "no net loss" provision to
ensure the protection and enhancement of forest cover in the county. Approval of this
clearing exemption would be conditional on trees being replanted in a suitable location
under the direction of a qualified forester at the applicant's expense.
If you have objections to this proposed clearing please reply in writing to the Elgin
County Tree Commissioner, c/o Kettle Creek Conservation Authority, R.R. #S, 44015
Ferguson Line, St. Thomas, Ontario, N5P 3T3, by the 14th day of November 2014.
If you have any questions regarding this notice, please contact the undersigned at (519)-
631 -1270.
Y
Jeff awrence
Elgin County Tree Commissioner
•
County of Elgin
Administrative Services
450 Sunset Drive
St. Thomas, On N5R 5V1
Phone: 519 - 631 -1460
www.elgin- county.on.ca
Progressive by Nature
Norma Bryant
From: Scott Gawley <sgawley @westelgin.net>
Sent: October -27 -14 4:18 PM
To: Norma Bryant
Subject: FW: Criminal Record Checks - Dutton Office
For the agenda
R. Scott Gawley, CPA, CGA
Administrator/Treasurer
Municipality of West Elgin
sgawlevCa)westelgin. net
519- 785 -0560
From: Fishleigh, Bradley (JUS) [ mailto :Bradley.Fishleigh @opp.ca]
Sent: October -27 -14 2:11 PM
To: Cameron S McWilliam; Bernhard Wiehle (bwiehle @elgin- county.on.ca); jamcintyre @elgin- county.on.ca; Scott Gawley
(sgawley @westelgin.net); CAO@duttondunwich.on.ca; cao @southwold.ca
Cc: douglasgunn@gunn.on.ca; Mark McDonald; Wayne Casier (wdcasier @gmail.com); Dave Marr; Bonnie Vowel
(bjvowel @execulink.com); jijcferquson@execulink.com; Wright, Kathy (JUS); Cox, Nancy; Herron, Deb (JUS); Landry,
Helene G (JUS); Carlson, Troy (JUS); Defoe, Greg (JUS); Doughty, Andy (JUS); Gordon, Al (JUS); Johnson, Brian (JUS);
Bennett, Lynn (JUS); McClure, Aaron (JUS); Quenneville, Andrea (JUS)
Subject: Criminal Record Checks - Dutton Office
All,
I regret to inform you Elgin County OPP will no longer be able to provide Criminal Record checks at the Dutton
office and November 7th will be the last day this service will be available at the Dutton office. With the increased safety
measures required as a result of recent events I can no longer allow administrative staff to be alone at the Dutton office
and it is not fiscally responsible to have an officer assigned to be at the office with the administrative staff. After Nov 7th
all criminal record checks will be completed at the OPP Detachment located at 42696 John Wise Line.
I am however pleased to advise that we are currently fully staffed and in most cases a standard criminal record check
with vulnerable sector check can be completed in about 15 minutes as long as the person has all the appropriate
documentation and identification. This means in most cases if the person is able to wait for completion they can leave
with their criminal record check in hand. Persons attending the office for criminal record checks are encouraged to call
first to ensure they have the correct forms.
It is very unfortunate we can no longer provide this service at the Dutton office however we will continue to work with
our communities to meet your needs the best way we can.
Kind Regards,
elad 9a/deep(
Inspector, Detachment Commander
Elgin County Detachment
519 631 -2920 (w)
519 317 -2223 O
"If you have any accommodation needs or require communication supports or alternate formats, please let me
know ".
Evergreen Cemetery
Located at 24928 Pioneer Line,
Municipality of West Elgin
Elgin County
West Lorne, Ontario
Oct. -18 -2014
Municipality Of West Elgin,
Public Works Superintendent
Lee Gosnell,
This letter is a request to the municipality for aid in the
maintenance of the roadway in the cemetery.
We have very much appreciated the snow removal you provide as
needed, during the winter.
At present, there are a number of potholes in the road way. These
pothole areas seem to be growing with this continuing wet weather.
If you could provide some gravel or assistance with the road way
maintenance it would be much appreciated. The other request involves the
trimming of cedar trees along the East entrance. It is difficult to see oncoming
traffic with the trees in the way.
I would be available to have conversation or meeting regarding this
situation at your earliest convenience.
There is an Evergreen Cemetery meeting scheduled for Nov. 5, 2014
at the Community Complex at 1:30pm in West Lorne.
I would hope to give a report of our solution to the plot holders at
that meeting.
Sincerely,
Robert A Morrison
President,
Evergreen Cemetery Plot Holders
519 860 0914
Ministry of Energy
Office of the Minister
4th Floor, Hearst Block
900 Bay Street
Toronto ON M7A 2E1
Tel.: 416- 327 -6759
Fax: 416 -327 -6754
OCT 29 2014
Ministers de I'Energie
Bureau du ministre
40 stage, edifice Hearst
900, rue Bay
Toronto ON M7A 2E1
TeI.: 416 327 -6758
Telec.: 416 327 -6754
Ms Norma I. Bryant
Clerk
Municipality of West Elgin
22413 Hoskins Line, Box 490
Rodney ON NOL 2C0
L:e.i:CMAL.11.1: k.40314
GECEI1 +Kb
1 231
MC- 2014 -2222
Dear Ms Bryant:
Thank you for your letter regarding wind energy. I welcome the opportunity to respond.
The collective success of Ontario's municipalities is critical to the success of the province of
Ontario. Municipalities have made it clear that they want a stronger voice in renewable
energy development and the government has taken steps to make that happen.
I appreciate the opportunity to explain the measures our government is implementing for
future procurements and the role municipalities can play in providing input into the
development process for existing renewable energy projects.
As Council will know from previous correspondence to Mayor Wiehle, on June 12, 2013,
I directed the Ontario Power Authority (OPA) to end the procurement of large renewable
energy projects through the Feed -in Tariff Program and to develop a new competitive
procurement process to allow for the consideration of future contract awards for cost - efficient
and well- supported projects. I asked the OPA to engage with municipalities to help inform
the identification of appropriate location and siting requirements for future renewable energy
projects.
The new Large Renewable Procurement (LRP) process will provide municipalities with a
stronger voice going forward and additional opportunities to participate in the development of
renewable energy projects. The process includes an initial Request for Qualifications (RFQ)
to qualify applicants, followed by a Request for Proposals (RFP) to evaluate projects, which
can only be proposed by qualified applicants.
We remain committed that this LRP will take into account local needs and considerations
before contracts are offered. Engagement activities in the LRP are intended to initiate early
relationship - building between developers and municipalities, and provide an early opportunity
for municipalities to advise of local needs and considerations to inform the design of a project
pre - contract.
As part of the OPA's extensive outreach activities to inform the development of the LRP, it
developed preliminary sets of RFQ stage evaluation criteria and possible RFP stage
components. These and other related materials were discussed with a wide variety of
stakeholders and communities between December 2013 and February 2014.
..- /cont'd
-2-
As part of these events, the OPA held four regional community meetings — in Chatham -Kent,
Sudbury, Orillia and Napanee — for municipalities, local distribution companies and the
general public. More than 850 groups and individuals participated in these activities and
more than 65 made written submissions. The OPA and ministry staff also met with
representatives from Association of Municipalities of Ontario task forces (Planning, Energy
and Economic Development).
On July 14, 2014, the OPA posted the final RFQ, which was open for submissions until
September 4, 2014. A preliminary RFP Framework document was also posted for public
review and comment until September 2. An extensive list of community engagement criteria
was included in the Framework document. For latest updates on the LRP program, please
visit the OPA's website at www.powerauthority.on.ca/Irp.
The OPA will continue to accept feedback from municipalities in advance of the posting of the
draft LRP RFP in October 2014. If you have not had the opportunity to submit your
comments, you can send them to the OPA directly by email at LRP @powerauthority.on.ca.
Regarding projects that are currently under development, the Ministry of the Environment and
Climate Change's Renewable Energy Approval (REA) process requires developers to ensure
multiple opportunities for local communities to provide input during the planning and
approvals process for wind projects. A minimum of two public meetings must be held about
proposed wind projects.
Municipalities continue to have a role to play in discussing site - specific issues covered by the
REA process. We encourage municipalities to engage in a constructive dialogue with
developers to help inform the REA process for a particular project.
We believe that the Green Energy Act and its regulations have been a success, and have
helped establish Ontario as a North American leader in clean energy. We have no plans to
change this course of action. That said, we welcome and appreciate the involvement of our
municipal partners in these crucial decisions about our electricity grid.
Thank you again for taking the time to share Council's views,
Sincerely,
Bob Chiarelli
Minister
c: Jeff Yurek, MPP, Elgin -- Middlesex— London
Joe Preston, MP, Elgin— Middlesex — London
Christina Cindric, MPP Liaison, Minister's Office
eWest Elgin
Community
Health Centre
22413 Hoskins Line
PO Box 490
Rodney, Ontario
NOL 2C0
October 30, 2014
Every
One
Matters.
Dear West Elgin Council Members:
On behalf of the West Elgin Community Health Centre, I would like to extend our sincere
thanks for your generosity and support for our annual Fall Family Fun Night. Our records
indicated that 278 people attended the event, including families, volunteers and service
providers. In addition to WECHC, 11 local agencies participated.
Thanks you for waiving the fee for the use of the Rodney Recreation Centre. By waiving the
fee, you assisted us in providing a completely free event to this community.
I am also writing this letter to formally request the use of the entire Rodney Recreation
Centre on Wednesday, October 28, 2015 from 12:00 pm -9:00 pm. Once again, we request
your consideration for waiving the fee, so that we can continue to offer this event to our
community's children and families free of charge.
Thank you for continuing to help make Fall Family Fun Night a success.
Sincerely,
Melanie Silos - Crowell, MSW, RSW
153 Main Street,
West Lorne, Ontario hioL 2P0
T 519- 768 -1715 F 519 - 768 -2548
info @wechc.on.ca
•
" -; 3 2014
The West Elgin Community Health Centre team works with our
communities and our partners to provide accessible, high quality
health care, health promotion and community support services.
www.wechc.on.ca
Nov, 10. 2014 12.:58PM
CORPORATION OF THE COUNTY OF ELGIN
NOTICE OF APPLICATION FOR CONSENT
APPLICATION NO. E 81114
PART LOT 19, CONCESSION 7, MUNICIPALITY OF WEST ELGIN
TAKE NOTICE that an application has been made by HENK AND ANS DIEKER,
24242 Downie line, WEST LORNE, Ontario, NOL 2P0, for a consent pursuant to Section 53 of
the Planning Act, 1990, as amended, to sever lands municipally known as 12538 Graham Road,
legally described as Part Lot 19, Concession 7, Municipality of,West Elgin.
The applicants propose to sever a lot with a frontage of 75 metres along Graham Road by a
depth of 83 metres (north lot line) to 99 metres (south lot line), Area 0.825 hectares (2 acres)),
containing one house and one shop, proposed to create one new lot surplus to the needs of the
applicants. The owners are retaining 34.4 hectares, proposed to remain in in agricultural use.
The location of the property is shown on the Key Map below:
ADDITIONAL INFORMATION regarding the application is available for inspection daily, Monday
to Friday, between 8:30 A.M. and 1:30 P.M., at the County Municipal Offices, 450 Sunset Drive,
St. Thomas or at a Public Hearing to be held on:
WEDNESDAY DECEMBER ,5t Din Committee Room #, County Municipal Ofices40 Sunset rive, St. Thomas.
Any person or public body may attend the Public Hearing and/or make written or verbal
representation either in support of, or in opposition to the proposed consent.
If you wish to be notified of the decision of the Land Division Committee in respect of the
proposed consent, you must submit a written request to the Land Division Committee. This will
also entitle you to be advised of a possible Ontario Municipal Board Hearing, Even if you are the
successful party, you should request a copy of the decision since the Land Division Committee
decision may be appealed to the Ontario Municipal Board by the Applicant or another member of
the public.
If a person or public body that files an appeal of a decision of the Land Division Committee in
respect of the proposed consent does not make written submission to the Land Division
Committee before it gives or refuses to give a provisional consent, the Ontario Municipal Board
may dismiss the appeal.
Dated at the Municipality of Central Elgin this 10th day of November 2014.
KEY MAP: (not to scale)
No. 2512 P. 2
-b-to
Progressive by Nature
Susan D. Galloway
Secretary Treasurer
Land Division Committee
450 Sunset Drive
St, Thomas, Ontario
N5R 5V1
County of Sign,
Enginesirng Services
450 Sunset Olive
St Thome% On N5R 5Y1
Phone; 510. 531,14130
vrww.ei en •county.on,ce
October 29, 2014
Four Counties Health Services site Strathroy Middlesex General Hospital site
1824 Concession Drive 395 Carrie Street
Newbury ON NOL 1 ZO Strathroy ON N7G 3J4
519 693 -4441 519 245 -1550
www.mhalilance,on.ca
Dear Municipal Leaders:
Re: MHA Strategic Planning Process Consultation Meeting with Regional Partners
The Middlesex Hospital Alliance has recently begun a strategic planning process that will guide our
organization over the next 3- 5- years. The development of a new strategic plan will revitalize and
refocus our energies. It also affords us the opportunity to engage partners in shaping an inspired
future.
The Board has retained the services of Whaley & Company (consultants Jim Whaley and Dave
Coulson) to support and guide our planning process.
As part of their initial investigation into strategic priorities for MHA, Messrs. Coulson and
Whaley would like to host a focus group with municipal representatives to discuss challenges
and opportunities for MHA and its two sites as it plans for the future. Your contributions will be
valuable to MHA and I hope that you will be able to take time to participate.
On behalf of the MHA I would like to thank you in advance for joining in our strategic planning
process and for considering this request. -
This focus group has been scheduled for Tuesday, November 18, 2014 at 7 pm in the Boardroom
at FCHS. Please RSVP to cathy.swan@mha.tvh.ca.
Should you have any questions please do not hesitate to contact either of us at your convenience.
Sincerely,
Kenneth J. Williams
MHA Board Chair
Todd Stepanuik
President & CEO
Connecting with the Future of Care
October 29, 2014
Municipality of West Elgin
PO Box 490
22413 Hoskins Line
Rodney ON NOL 2C0
ELGIN ST. THOMAS
PUBLIC HEALTH
RE: Healthy Communities Partnership
Dear Mayor Bernie Wiehle and Council,
In response to the recent municipal election, the Healthy Communities Partnership needs to
request that each municipality once again appoint a political representative to this committee.
The Partnership is an advisory committee that meets during the day approximately 6 times per
year and exists to support municipalities in creating a healthy community. Our most recent
success was the creation and adoption of the Elgin St Thomas Cycling Master Plan by your
municipality and all others.
If you would like additional information on the Healthy Communities Partnership please contact
Erica Arnett, Health Promoter at 519 -631 -3159 ext 247 or via email at
earnett@elginhealth.on.ca. I am available to make a presentation to your Council on the
Partnership and its work.
Thank you in advance for responding to my request.
Yours sincerely,
Erica Arnett
Health Promoter
NOV d ; 2119
Elgin St. Thomas Public Health
1230 Talbot Street, St. Thomas, ON N5P 109
Phone: 519 -631 -9900 Toll Free 1 -800- 922 -0096 Fax: 519 - 633 -0468 Voicemail: 519 -631 -3159
www.elginhealth.on.ca
TOWN OF COLLINGWOOD
October 20, 2014
Canada Post
955 Highbury Ave
London, ON N5Y 1A3
Attn: Deepak Chopra, Chief Executive Officer
Andy Paterson — Municipal Relations
-and-
Sara A hriaas, Ct� rk
97 Fiurontario St. P.O. Box 157
Collingwood, ON L9Y 3Z5
Tel: (705)445 -1030 exl. 3225
Fax: (705)445.2449
Email: saimasecollingwood.ca
Mayors, Reeves, Wardens and Councils — Ontario Municipalities (via email)
Re: Reconsider Decision to Eliminate Home to Home Postal Delivery
During the meeting of Council held September 22, 2014, Council of the Town of Collingwood passed the
following resolution:
Moved by Councillor Ian Chadwick Seconded by Councillor Kevin Lloyd
WHEREAS Canada Post has proposed a plan to end residential home delivery in Canada;
AND WHEREAS the lack of home delivery will disadvantage many seniors and people
with mobility problems and will be compounded during inclement weather;
THEREFORE BE IT RESOLVED THAT the Town of Collingwood does not support the
proposed plan to eliminate residential home to home delivery and herein petition Canada
Post to reconsider this plan immediately and retain this valuable service for communities.
AND FURTHER THAT a copy of this resolution be forwarded to the Association of
Municipalities of Ontario (AMO), Federation of Canadian Municipalities (FCM),
municipalities in Ontario, as well as to our local MP, MPP and representatives of Canada
Post and its unions to encourage others to speak up against this plan.
CARRIED (Recorded Vote 8 -1)
Home to home mail delivery is essential for seniors and persons with varying abilities within our
community. If home to home delivery was discontinued and replaced with the community mailbox, it
would deny these individuals of a fair and barrier free opportunity from accessing regular mail delivery
and adversely affecting their quality of life. In addition, this change will also have a residual impact on the
employees, local post offices, and economy. We are strongly urging Canada Post to reconsider their
decision and are seeking support from municipalities across Ontario and the Country.
Yours truly,
TOWN OF COLLINGWOOD
Almas
Clerk
Cc Association of Municipalities of Ontario {AMC)
Federation of Canadian Municipalities (FCM)
Kellie Leitch MP
Jim Wilson MPP
Norma Bryant
From: Scott Gawley <sgawley @westeigin.net>
Sent: November -07 -14 12:05 PM
To: Norma Bryant
Subject: Fw: Emergency /evacuation policy
?For the Nov 13 agenda
D-Iq
Sent from my BlackBerry 10 smartphone on the Bell network.
A Original Message •
From: beattiehaven(c'D,bellnet.ca
Sent: Friday, November 7, 2014 11:26 AM
To: sgawleya(westelgin.net
Cc: adrnin a( ..rhra.i- sight.com; DOC
Subject: Emergency /evacuation policy
Hi Scott just a reminder of a converstion we have had over the last couple of weeks to ensure that Beattie Havens
request to be included as a group identified to use the West Elgin Recreation centre in case of an emergency /evacuation
at Beattie Haven. Norma advises there is a council sitting on Nov.27 /14 that we hope our request would be address on
the agenda. Please advise if this is possible. The request would also include the use of the 4 County Transit bus as well.
Also wondering how long it would take, assuming approval, to get a "memo of understanding" signed by the county. The
people at RHRA are requesting this info from Beattie Haven. Thanks Scott and talk later glenn degraw
1
West Elgin Arena Board
E-I
Tuesday September 9 2014
This session of the West Elgin Arena Board was called to order at 9:30 am with the following members
present: Mary Bodnar, Alphonse Willie, Bob Purcell, Dug Aldred and Recreation Superintendent Jeff
Slater.
Item # 1 Disclosure of Pecuniary Interest: None noted.
Item it 2 Delegations: None present
Item # 3 Adoption of the Minutes:
Moved By: Bob Purcell
Seconded By: Dug Aldred
The West Elgin Arena Board resolves that the minutes of August 12 2014 be approved as presented.
CARRIED.
Item # 4 Accounts and f=inancial Reports:
Moved By: Alphonse Willie
Seconded By: Dug Aldred
The West Elgin Arena Board resolves that the accounts in the amount of $ 1126.60 be hereby approved
for payment.
CARRIED
Item it 5 Business Arising from the Minutes:
• Concession: The Recreation Superintendent indicated that he had discussed this winters
operation with Mr. Kool and that Mr. Kool indicated that he probably would not be open until
the first week in October and probably not for lunch time during the week.
• De- Humidifiers: The Recreation Superintendent indicated that the ice was going in, a slow
process this year due the extreme heat that we are having. The de- humidifiers were not keeping
up. The ice was being painted white as we were meeting.
Item # 6 Correspondence: No correspondence was received.
Item # 7 New Business: No new business was presented.
Item # 8 Adjournment:
The West Elgin Arena Board resolves that this session of the West Elgin Arena Board hereby adjourn at
this hour of 10 am and reconvene at 9:30 am on October 14 2014 or at the call of the chair.
CARRIED
E -
West Elgin Arena Board
Regular Session October 14 2014
Thus session of the West Elgin Arena Board was called to order at 9:30 am with the following members
present: Bob Purcell, Alphonse Willie, Mary Bodnar, Dug Aldred and Recreation Superintendent Jeff
Slater.
Item # 1 Disclosure of Pecuniary Interest: None noted.
Item # 2 Delegations: None were present.
Item # 3 Adoption of the Minutes:
Moved By: Alphonse Willie
Seconded By: Dug Aldred
The West Elgin Arena Board resolves that the minutes of September 9 2014 be approved as presented.
CARRIED
Item # 4 Accounts and Financial Reports:
Moved By: Dug Aldred
Seconded By: Bob Purcell
The West Elgin Arena Board resolves that the accounts in the amount of $ 8590.75 be approved for
payment.
CARRIED
Item # 5 Business arising from the Minutes:
• Concession Operation: The concession operators are back and are operating at lunch time as
well this year.
• WLMH: The Girls Tournament is scheduled for January 16 and 17 2014. Alphonse also inquired
as to whether or not we could get the front door to close faster. At the current slower speed it
might cause problems with the winter winds blowing into the entry way. Possible solutions
included getting the door to close faster, and or installing a partial wall under the overhang that
we currently have. Arena staff will monitor the issue.
• De- Humidifiers: The Recreation Superintendent reported that they have had significant issues
with the de- humidifiers, in as much as they were not operating during the ice installation
process, not a great time to be inoperative. The ice users would have definitely notice the issue.
Both have been repaired and are operating as intended.
Item # 6 Correspondence: No correspondence was presented at this session.
Item # 7 New Business:
• Helmets: All Arena / Recreation Staff are required to wear CSA Hockey Helmets while doing any
work on the ice surface or operating the Zamboni. The Recreation Superintendent reported that
the helmets were purchased in late September and distributed to the staff. Documentation was
prepared and the staff has signed the documents. Staff are required to wear the helmets at all
times while working on the ice and operating the Zamboni. Further staff are required to wear
the ice cleats also provided when working on the ice surface. It is not mandatory that the cleats
-2-
be worn when shovelling the ice as part of the resurfacing process, however they are there
should staff desire to wear them for this process.
• Men's Hockey League: Discussion took place regarding the upcoming men's Hockey league. The
Recreation Superintendent will contact the organizer regarding ice time requirements.
• WESC: The Arena Board would like to meet with the WESC, Lisa Jacques to discuss the future of
the club and any other pertinent issues, The Recreation Superintendent will contact the WESC to
try and arrange mutually convenient meeting date.
ITEM # 8 Adjournment:
Moved By: Dug Aldred
Seconded By: Alphonse Willie
The West Elgin Arena Board resolves that this session of the West Elgin Arena Board hereby adjourn at
this hour of 10:15 pm and reconvene November 4 2014 bat 9:30 am or at the call of the chair.
CARRIED.